a full view of Building 32 from the soccer fields, showcasing its colorful mural

Bond Facilities Report

Thank you, Lane voters! See the latest report (July 1, 2026) on Bond Updates.

2020 Bond Expenses 

  • Expenses - Inception to date: $131,471,789.39
  • Outstanding Encumbrances: $23,396,348.32 
    • Includes state capital construction and seismic grants.

Building 16 - Math & Science Improvements

Public areas of the east wing reopened to the public for the start of the spring term. Work continues
to furnish and equip refurbished classroom and lab areas for full occupancy for the Fall term of 2026.
Site improvements will continue through the summer.

Schedule:

  • Design Start: April 2023

  • Construction Start: March 2025

  • Construction Completion: September 2026

Consultant Team:

  • Architects: Rowell Brokaw Architects

  • Construction Manager/General Contractor: Fortis Construction

Budget:

  • Total Project: $31.3 Million [$8.0M State Capital Construction funds + $23.3M Bond funds]

  • Construction Cost: $20.4 Million

Project Details:

LCC is undertaking a comprehensive renovation of the Science, Mathematics, and Engineering laboratory facilities. The work will reconfigure existing teaching and laboratory spaces to contemporary laboratory design standards, including the installation of new equipment and the integration of communications and presentation capabilities. New space layouts, equipment, and lighting will improve student safety and allow improved instructional support during lab activities.

Renovations to common areas will improve accessibility and encourage exposure of science activities to a more diverse student profile. The renovation will also provide undergraduate research space and take care of much of the deferred maintenance backlog on this building.

Instructional Programs & Services:

  • Science, Math, and Engineering

Building 15 / Public Safety Relocation

This project is being tracked as three phases of work.

Public Safety Relocation

  • This project is a critical path item for Building 12 demolition. Building 15 was identified in the 2020 Master Plan as a new location for Public Safety offices. Construction has started with interior demolition.

Elevated Platform Remediation

  • Sections of the raised platform west of Building 15 are to be removed to address deferred maintenance and structural deficiencies. Sitework on the lower level will improve access for emergency response and service vehicles. Construction has started with mass excavation on the east side of the building with the goal of completion before the start of fall term 2026.

Building Access and Parking

  • The use of Building 15 for Public Safety will require changes to the building entry, egress pathways, and the development of dedicated parking for departmental vehicles. Excavation and site work are underway with the goal of completion before the start of fall term 2026. Construction is to be coordinated with the Public Safety Relocation and Elevated Platform Remediation projects.

Building 12 Demolition and Site Restoration

Site improvements with the demolition of Building 12 will improve pedestrian and emergency access in the southeast quadrant of the campus. Enhanced circulation pathways will create a new eastern gateway to the campus core.

  • Bidding and contracting of the work were completed in conjunction with the Building 15/ Public Safety Relocation Projects.
  • Demolition and construction are anticipated to begin in the summer of 2027, following the relocation of Public Safety to Building 15.

IT Infrastructure

Cyber Security

  • Replacement and upgrades to campus computers are substantially complete.
  • CRAC Unit Replacement: Design work for the replacement of the cooling and ventilation systems in the campus data center is underway

    Network Upgrades

  • IT Network Switch Replacement: All campus network switches have been replaced.
  • IT WiFi Upgrade: Contracts for a new and expanded WiFi system and for installation of the system are before the board at the July meeting. Planning for the installation is underway. System replacement is planned for completion by the end of 2027.

    Classroom Modernization

  • Classroom upgrades at the Mary Spilde Downtown Center were completed.  Additional classroom upgrades are planned at the main campus. 

Safety & Security

  • Security Camera Replacement
    • Phase I of this work is completed.
  • Access Control Upgrade
    • Classrooms will be fitted with new lock hardware.
  • Campus-Wide Fire/Life Safety
    • Phase 1 of the fire alarm panels upgrade project is complete. A second phase of fire panel upgrades is in the planning and design phase.

Florence Center Seismic & Major Maintenance

  • Bond work on this project is complete. The total project cost is projected to be within budget.

Health Professions Building

  • Staff has completed project close-out. The total project cost is projected below $33M.
  • The artist has completed the mural.

Industrial & Trades Education Center (ITEC)

This project has been tracked as two phases of work:

  • AIR – Replacing the campus compressed air system is complete.
  • ITEC –  Bond staff continue to assist in upgrades to equipment and teaching environments.
  • Staff is in the final phase of project close-out. Total project cost is within the $48.5M budget. 

Athletic Fields

Track Resurfacing

  • This project was completed in the summer of 2020.

    Turf Replacement (soccer field and track infield)

    • This project was completed in the summer of 2024.

    Baseball Field Synthetic Turf Installation

    • Baseball Field Synthetic Turf Installation was completed in the summer of 2025.