Project Status - Construction Updates
(Visit the Facilities Construction Projects page)
September 1, 2009
HEALTH & WELLNESS BUILDING
The exterior work around building 4 is mostly complete, including ramps, rails and plantings. On Wednesday and Thursday, September 2-3, the contractor will be pouring floor slabs. The pours will start at 4:00 a.m. and will take four to five hours. Contact David Amundson, (541) 463-3455.
August 18, 2009
HEALTH & WELLNESS UPDATE
The contractor is continuing to install footings and backfilling foundation walls with gravel. On August 28, concrete trucks will be coming in from 4:00 a.m. to about noon for the concrete slab pour. Steel is expected to arrive September 7. Contact Todd Smith, (541) 463-5132.
June 12, 2009
HEALTH & WELLNESS UPDATE
Lease Cructher Lewis, CMGC (Construction Manager General Contractor), is continuing with site mobilization this week. The groundbreaking ceremony on June 2 was a success thanks goes to the Foundation, facilities staff, and everyone else who helped. The contractor will start the demolition of the tennis courts and the site excavation on June 15. Expect heavy truck traffic entering the north access road from Eldon Schafer Drive and exiting on Gonyea Road. The noise levels during the demolition and site prep will be from extreme to moderate. Contact Todd Smith, (541) 463-5132.
June 2, 2009
HEALTH & WELLNESS UPDATE
Lease Cructher Lewis, the CMGC (Construction Manager General Contractor), has their construction office trailer and the site fencing establishing the perimeter of the construction site in place. The groundbreaking ceremony is on June 2 and will start in the front entry garden at 3:30 p.m., then move to the building site for the ceremonial turning of the shovel. The contractor will start the demolition of the tennis courts and the site excavation on June 15. During this period of time we can expect heavy truck traffic on the north access road entering the college on Eldon Shafer Drive and exiting on Gonyea Road. The noise levels during the demolition and site prep will be from extreme to moderate. Contact Todd Smith, (541) 463-5132.
May 12, 2009
HEALTH & WELLNESS BUILDING UPDATE
The groundbreaking ceremony is scheduled for June 2 at 3 p.m. The designers are finalizing interior materials. Beginning June 8, the designated parking for dental patients and other health careers parking in the east and middle row of parking lot A will be relocated to parking lot B. The contractor will begin staging equipment and materials in parking lot A. No through traffic will be allowed on the fire lane south of building 4 except for emergency and contractor vehicles and equipment. Equipment will be arriving from the east and exiting west toward Gonyea Road. Contact: Todd Smith, project coordinator, (541) 463-5132.
May 5, 2009
HEALTH & WELLNESS BUILDING GROUNDBREAKING SET FOR JUNE 2
Weekly project meetings with the Lease Crutcher Lewis, construction manager/general contractor, and SRG Partnership, Inc., architect, began Monday, May 4. Groundbreaking is scheduled for June 2 and construction on the site is scheduled to begin June 15. For more information contact Project Coordinator Todd Smith at (541) 463-5132.
April 14, 2009
HEALTH & WELLNESS AIMING FOR LEED GOLD STANDARD
Facilities, Management and Planning and Information Technology staff at Lane Community College have reviewed the latest drawings and provided input related to maintenance and operations for the Health and Wellness building. Architects are now developing construction documents and will prepare an updated cost estimate. The design currently meets U.S. Green Building Council Leadership in Energy and Environmental Design (LEED) silver standard and is two to three points from LEED gold standard. The general contractor is scheduled to mobilize and begin demolition of the tennis courts June 15. A contractor staging area will be established in the parking lots west of the tennis courts so there will be less parking in lot A for the next 12-15 months beginning in June. For more information contact Todd Smith at (541) 463-5132.
March 24, 2009
HEALTH and WELLNESS BUILDING UPDATE
Architects have completed the design development stage and are at the LEED silver standard (Leadership in Energy and Environmental Design). Designers and college facilities staff are looking at ways to reach LEED gold. The next cost estimate will be available in two weeks. The project is on schedule for a June 15 groundbreaking. Once the construction phase of the project begins, there will be equipment and trucks traveling on Eldon Schafer Drive through Parking Lot N, and on the north access road next to the athletic fields. Contact: Todd Smith, (541) 463-5132.
March 17, 2009
CONGRESSMAN DEFAZIO HELPS SECURE $330,000 FOR LANE
The federal omnibus spending bill signed into law by President Obama on March 11 includes $330,000 for Lane nursing labs and equipment. Congressman Peter DeFazio worked for the appropriation over the past year. Last month, DeFazio met with Lane officials attending a summit of the Association of Community College Trustees and American Association of Community College in Washington D.C. See the photo at www.lanecc.edu/mpr/success/index.htm.
|
|