Link: Lane Home
 Lane Home Page  |  Search Lane
Contact Us  |  Web Site Accessibility
Community Center for Family Counseling

>> Planning and Construction
  
>> Indoor Environmental Quality
 
Construction Projects
>> Deferred Maintenance
>> Bond
>> Health and Wellness
>> Longhouse
   
>> Trades and Services
   
 
>> Facilities Office
   
>> Transportation
   
>> Safety
   
>> Space Assignment Requests
  
>> Work Requests
  
>> Resources
    
>> Related Sites
   

 

Deferred Maintenance Project Updates

Building 1 | Building 2 | Building 3 | Building 4 | Building 5 | Building 6 | Building 7 | Building 8 | Building 9 |Building 10 | Building 11 | Building 12 | Building 13 | Building 15 | Building 16 | Building 17 | Building 18 | Building 19 | Building 24-27 | Center | Airport | Downtown Center | Florence Center | Parking Lots

October 27, 2009
PROJECT 446 EXTERIOR LIGHTING
The contractor, Christenson Electric, has completed the placement of path lighting fixtures. Parking lot fixtures work is mainly complete. Six of the old fixtures in parking lot B will be replaced and the poles relocated later this year by LCC electricians. Rather than trimming and causing severe damage to the trees, the decision was made to relocate the light poles. The replacement of a row of fixtures in parking lot L has been delayed as the wrong fixture was shipped by the manufacturer. The LCC electricians will continue to replace the light fixtures on the outside of buildings through fall term. Contact Dave Smith, 3433.

PROJECT 447 CARPET REPLACEMENT/FLOOR COVERING
Building 16 entry mat replacement is half complete; remaining work scheduled for October 24.

Building 3 College Finance carpet replacement is scheduled for October 30 – November 9. Installation of building 19 hard flooring in hallway is scheduled for October 31 – November 1, and the storage hallway to be completed over winter break. The Flight Technology, building 44, carpet replacement is tentatively scheduled for December. Contact Angela Fazio, 3428.

PROJECT 448 KEYLESS ACCESS
Work continued on the keyless access project in the Math & Science building 16 and in various other campus buildings. The contractor, Allied Fire & Security, will be moving to nights the week of October 25 in order to be more productive in the occupied classroom buildings. The LCC electricians, also working nights, are working on the electrical conduit in buildings 5, 6, and 11. The first buildings to be implemented will be buildings 8, 9, and 12. The door hardware installation is scheduled to begin late October and be completed in November. The remainder of the buildings will be commissioned through winter term. Contact Dave Smith, 3433.

PROJECT 449 ASBESTOS ABATEMENT
Deferred maintenance crew continues installation of insulation on fittings throughout the tunnel system and soon will begin installing new insulation on the pipes in the mechanical rooms. New PVC insulation covers for Victaulic fittings will be tried out next week. Contact Angela Fazio, 3428.

PROJECT 450 EMERGENCY COMMUNICATION SYSTEM
The contractor has been contracted to update and replace the fire alarm system at the Florence campus. This work will be done in time for the beginning of winter term. The contractor, SecureCom, is working an off shift on the Eugene campus to minimize impact of their work on the LCC community. Due to a delay in shipment of certain components, the testing of much of the fire alarm systems will be delayed until the first week of winter break, December 14 – 20, to minimize impacts on faculty, staff, and students. All buildings are currently protected, and will continue to be, by existing fire alarm systems. Contact Dave Smith, 3433.

PROJECT 451 UTILITY SUBMETERING
Installation of all meters completed (domestic hot and cold water, natural gas, chilled and heating water and electrical). Installation of communications wiring is 90 percent complete. Operations and maintenance manuals were received. The final walk through to be scheduled. Anticipated metering project completion estimated to be late October. Replacement cold water main valves complete. Contact Angela Fazio, 3428.

PROJECT 452 ELECTRICAL UPGRADES
Electrical panels were replaced buildings 5, 11, and 12. The remaining panels identified for replacement will be replaced later this year or early 2010. Contact Dave Smith, 3433.

PROJECT 454 BUILDINGS 4 AND 5 REROOF
Carlisle inspection of fleece-back TPO roof carried out this week. Umpqua is working on punch list items. Cosmetic issues with skylight between buildings 4 & 5 have been resolved and rework to be scheduled. Contact Angela Fazio, 3428.

PROJECT 455 RESTROOM UPGRADES
Contract work complete. Contact Angela Fazio, 3428.

PROJECT 456 CLASSROOM UPGRADES
Upgrade to a smart classroom at Flight Technology will begin the week of November 9. Contact Angela Fazio, 3428.

PROJECT 458 AMTF IMPROVEMENTS
Building 12 paint booth repair work begins this week. Final commissioning reports to be generated. RTS paint booth work on hold pending airport/city approval of temporary construction equipment. Contact Mark Richardson, 3456.

PROJECT 459 SHOWER UPGRADES
Men and Women Locker Room Upgrade Project complete with minor punch list items. Contact Angela Fazio, 3428.

October 27, 2009
PROJECT 445 STAIRS AND HANDRAILS
Building 4 and 5 handrail stairs are complete and inspected. Friction tape to be added to step nosings to increase safety. Contact Brian McMurray, 5829.

PROJECT 445 ELEVATOR MODERNIZATION
Elevator is permitted and in operation. Punch list completion to be scheduled. Contact Brian McMurray, 5829.

PROJECT 447 CARPET REPLACEMENT/FLOOR COVERING
Classrooms located at the main campus scheduled for carpet replacement are now completed. Building 16 entry mat replacement is half complete; remaining work scheduled for October 24. Building 3, College Finance, carpet replacement is scheduled for October 30-November 9. Building 19 hard flooring to be installed in hallway is scheduled for October 31-November 1. The storage hallway flooring installation is to be completed over winter break. Flight Technology asbestos survey identified problem in building 43. Building 44 carpet replacement to be scheduled. Contact Angela Fazio, 3428.

PROJECT 449 ASBESTOS ABATEMENT
Deferred maintenance crew continues to wrap insulation on fittings throughout tunnel system and soon will begin insulating the pipes in the mechanical rooms. Contact Angela Fazio, 3428.

PROJECT 451 UTILITY SUBMETERING
Installation of meters on domestic hot and cold water, natural gas, chilled and heating water and irrigation is complete; 28 of 29 electrical meters installed. Twenty percent of the communications wiring has been installed and anticipate metering project completion by October 31. Replacement cold water main valves complete. Replacement of hot water main valves anticipated over winter break. Contact Angela Fazio, 3428.

PROJECT 454 BUILDINGS 4 AND 5 REROOF
Umpqua to complete work on identified punch list items this week. Manufacturers plan to inspect completed work next week. Contact Angela Fazio, 3428.

PROJECT 454 CENTER BUILDING REROOF
Contract work complete. Deferred Maintenance workers fabricated access stairs to the roof. Fabrication and installation of handrails will follow. Contact Angela Fazio, 3428.

PROJECT 455 RESTROOM UPGRADES
Contract work complete. Problems with existing exhaust systems to be investigated by FMP. Contact Angela Fazio, 3428.

PROJECT 456 & 457 CLASSROOM UPGRADES
The deferred maintenance portion of classroom upgrade projects is complete. Chair rails that have been requested in several classrooms and hallways to be completed by FMP. Contact Angela Fazio, 3428.

PROJECT 458 AMTF IMPROVEMENTS
Building 12 paint booth repair work begins this week. Final commissioning reports to be generated. RTS paint booth work on hold pending airport/city approval of temporary construction equipment.

September 15, 2009
PROJECT 445 STAIRS AND HANDRAILS

Handrails for building 4 stairs are on order. Installation is expected to begin during the week of September 21. Contact Brian McMurray, 463-5829.

PROJECT 445 ELEVATOR MODERNIZATION
Work on the north elevator in the Center Building is nearing completion. Inspection in expected during the week of September 21. Alternative access to the Titan Store is being provided on the south elevator. Contact Brian McMurray, 463-5829.

PROJECT 446 EXTERIOR LIGHTING
The contractor, Christenson Electric, is finalizing the placement of path lighting fixtures (pole mounted and bollard) around building 3 and on the pathway south of building 12. The taller pole mounted fixtures provide general pathway lighting and bollards, the short three-foot high round fixtures, denote the exit paths from the campus interior to parking lots. Currently, lot fixtures are being installed in parking lot B by the LTD bus station. The installations of fixtures continue and will be nearly complete by the beginning of fall term. The light from the new LED fixtures is a noticeable white as compared to the familiar yellow glow produced by the old high pressure sodium fixtures. Contact Dave Smith, 463-3433.

PROJECT 448 KEYLESS ACCESS
Work continues on the keyless access project associated with the replacement of the north elevator in the Center Building. The proximity card will allow access to the Titan Store storage area on the first floor. The elevator should be inspected next week and approved for operation shortly thereafter. The buildings to be commissioned next include buildings 8, 9, 12, and 4 in October. Contact Dave Smith, 463-3433.

PROJECT 450 EMERGENCY COMMUNICATION SYSTEM
The fire alarm system in building 7 will be completed and tested next week. Due to a delay in shipment of certain components, plans to test fire alarm systems in other locations have been delayed until the first week of winter break, December 14-20, to minimize impact on faculty, staff and students. All buildings are and will remain protected by existing fire alarm systems. Contact Dave Smith, 463-3433.

PROJECT 451 UTILITY SUBMETERING
Installation of meters on electrical, domestic hot and cold water, natural gas, chilled and heating water and irrigation will allow for utility monitoring, performance evaluation and energy maximization. This phase of the project includes installation of all meters and start-up of electrical and heating water monitoring only. One hundred thirty of 131 plumbing meters have been installed. Electrical meters to be installed this week on Center Building and Flight Tech, which will complete 28 of 29 electrical meters. Electrical installation of the monitoring system is ongoing. Contact Dave Smith, 463-3433.

A second aspect of this project encompasses replacement of isolation valves on the main distribution system and to each building for domestic hot and cold water on main campus. As most of these valves were originally installed in the 1960's, replacement will greatly improve system reliability. All cold water valves have been replaced. Work continues on replacement of hot water valves. Contact Angela Fazio, 463-3428.

PROJECT 452 ELECTRICAL UPGRADES

Twenty of the 55 old and obsolete electrical panels have been replaced to date. The remaining 35 panels are located in buildings. 5, 11, and 12, and will be replaced later this year or early 2010. Contact Dave Smith, 3433.

PROJECT 455 RESTROOM UPGRADES

Building 4 first floor restrooms punchlist is completed. Final hook up on the second floor starts this week and workers anticipate completion by September 18.A department walk-through and turnover for use will occur during the week of September 21. Building 6 first floor restrooms are substantially complete. Punchlist items are scheduled to be completed by September 16 and a department walk-through and turnover by September 18. Contact Angela Fazio, 463-3428

PROJECT 458 AMTF IMPROVEMENTS
The paint booth in building 12 has been assembled and mechanical/electrical connections are being made. Expect completion during the week of September 28. The RTS building paint booth has been ordered and expected delivery is early October. Contact Brian McMurray, 463-5829.

PROJECT 459 SHOWER UPGRADES
Completion of the locker room upgrade is anticipated for September 18 with the department walk-through and turnover during the week of September 21. Contact Angela Fazio, 463-3428.

September 1, 2009
PROJECT 445 STAIRS AND HANDRAILS

Handrails for building 4 stairs are on order. Expect installation week of September 21. Contact Brian McMurray, 463-5829.

PROJECT 445 ELEVATOR MODERNIZATION
Work on elevator nearing completion with inspections scheduled for the week of September 7. Alternative access to the Titan Store is being provided on the south elevator. Contact Brian McMurray, 463-5829.

PROJECT 446 EXTERIOR LIGHTING
The contractor, Christenson Electric, continued to place path lighting fixtures (pole mounted and bollard) along egress paths on main campus. Parking lot fixtures are expected to be received during September and installed before September 29. Contact Dave Smith, 463-3433.

PROJECT 447 CARPET REPLACEMENT/FLOOR COVERING
Carpet replacement for building 19 upper level hallways and classrooms will be completed by September 2. Rubinstein’s Carpet removal on the first floor of building 19 is going to start on Monday August 31 and is expected to be completed by September 4. Building 19 room 104 is scheduled to have the carpet removed on September 3 and replaced on Friday, September 4. Flooring has been ordered for Flight Technology and is scheduled for installation October 30. Contact Mark Richardson, 463-3426.

PROJECT 448 KEYLESS ACCESS
Work continues on the keyless access project. The first system to be installed and commissioned will be the proximity card system associated with the Center building north elevator replacement. The proximity card will allow access to the bookstore storage area on the first floor. The elevator should be inspected next week with turnover to the college soon thereafter. The next buildings to be commissioned include buildings 7, 9, 12 and the child care buildings (interior cameras only). Contact Dave Smith, 463-3433.

PROJECT 449 ASBESTOS ABATEMENT
Abatement work for the tunnel system has been completed. The remaining mechanical room in the Center building is scheduled to be completed September 5-6. Deferred Maintenance crews will start back up in late September installing new insulation in the tunnels and mechanical rooms around campus. Contact Mark Richardson, 463-3426.

PROJECT 450 EMERGENCY COMMUNICATION SYSTEM
SecureCom, the fire alarm contractor, will begin testing fire alarm systems September 11 and continue through September 25. The LCC deferred maintenance electricians provided power to a number of fire alarm panels. Contact Dave Smith, 463-3433.

PROJECT 451 UTILITY SUBMETERING
Meter installations completed this week: water in buildings 41, 49, and Center; natural gas in buildings 44, 49 and Center; electric in buildings 10, 12, 13, 15, 16, 17, 41 and Center. Main isolation valve replacements this week: domestic cold water in buildings 12, 15, 16, 17, and Center. Contact Angela Fazio, 463-3428.

PROJECT 452 ELECTRICAL UPGRADES
Fifty-five old and obsolete electrical panels were identified as requiring replacement. Twenty of the panels have been replaced to date. The remaining 35 panels are in buildings 5, 11 and 12 and will be replaced later this year or next year. Contact Dave Smith, 463-3433.

PROJECT 453 SEWER PIPE REPLACEMENT
The broken pipe in Lagoon #2 is repaired and S2 mechanical is waiting for a valve that has been ordered to complete the project. The gate valve is scheduled to be replaced September 4. Both grease traps have been put into place in the Center building kitchen but additional parts were needed to complete the installation. The installation is expected to be completed by September 4 after the additional parts arrive. Contact Mark Richardson, 463-3426.

PROJECT 454 BUILDINGS 4 AND 5 REROOF
Roof installation for building 4 and 5 have been completed and the metal roofing contractor is expected to be completed by September 4. The skylights are still in manufacturing and they currently have an installation date of October 17. Contact Mark Richardson, 463-3426.

PROJECT 455 RESTROOM UPGRADES
Building 4 first floor restrooms punchlist is to be completed August 28. Building 4 second floor restrooms tile installation to be completed this week and cured. Final hook-up starting next week with anticipated completion September 18. Building 6, level 1 restroom plumbing, ceiling and partitions are complete. The restroom is substantially complete awaiting a new door September 3 and turnover with the new door on September 10. Contact Angela Fazio, 463-3428.

PROJECT 456 & 457 CLASSROOM UPGRADES
Classroom upgrades are on schedule to be completed by the fall term. This week, the project coordinator is going to start completing a walkthrough of the classrooms with the department personnel and others to get ready for the reopening of the classrooms in several buildings. LCC staff is currently working on installing the AV electronics but is not expected to have all smart classrooms completed by the start of fall tem. The focus for the LCC staff is to have some rooms in Center building and building 19 completed by fall term. Contact Mark Richardson, 463-3426.

PROJECT 458 AMTF IMPROVEMENTS
Bldg 12 paint booth has been assembled and mechanical/electrical connections are being made. Expect completion week of September 28. The paint booth for RTS building will be ordered this week. Contact Brian McMurray, 463-5829.

PROJECT 459 SHOWER UPGRADES
Tile installation is to be completed in final men’s area this week. Demolition of final women’s area to be complete so re-tiling can start this week. Forty percent of the tile area has been sealed. Anticipated substantial completion of the entire locker room upgrade project is scheduled for September 18. Contact Angela Fazio, 463-3428.

August 31, 2009
SUSTAINABILITY IN DEFERRED MAINTENANCE ROOFING PROJECTS
The Building 4 and 5 roofing projects include a significant improvement in roof insulation. Facilities estimates that this project will annually save 3,289 therms of natural gas and 96,296 kilowatt-hours of electricity, resulting in an annual decrease in energy costs of $8,336. This project contributes to Lane's goal to become carbon neutral. Contact Jennifer Hayward, 463-5594.

PROJECT 446 EXTERIOR LIGHTING
Christenson Electric, continued to place path lighting fixtures (pole mounted and bollard) along egress paths around campus, especially around Bristow Square. Parking lot fixtures are expected to be received during September and they will be installed by the start of fall term. Contact Dave Smith, 463-3433.

PROJECT 447 CARPET REPLACEMENT/FLOOR COVERING
Carpet replacement has been completed in the Center building classrooms. Installation efforts are now being redirected to building 19 where crews are going to start removing the old carpet in the hallways and lobby area. The carpet removal will be done after 5 p.m. and new carpet installation will be the following day. Contact Mark Richardson, 463-3426.

PROJECT 448 KEYLESS ACCESS
Work continues on the keyless access project. The first system to be installed and commissioned will be the Proximity Card system associated with the Center building north elevator replacement. The proximity card will allow access to the Titan Store storage area on the first floor. Contact Dave Smith, 463-3433.

PROJECT 449 ASBESTOS ABATEMENT
Abatement in the tunnels will be completed on Wednesday, August 26. Two mechanical rooms are left to be completed. In order to complete abatement in the Center building mechanical room, the air system is scheduled to be shut down for the building September 5 and 6. If an additional day is required, the air system will also be shut down on September 13. Contact Mark Richardson, 463-3426.

PROJECT 450 EMERGENCY COMMUNICATION SYSTEM
SecureCom, the Fire Alarm contractor, is working during the evening hours in building 19 this week to avoid disruption of the building occupants. Commissioning and testing of the fire Alarm system will begin on Friday, September 4 and continue through September 25. Contact Dave Smith, 463-3433.

PROJECT 451 UTILITY SUBMETERING
Completed meter installations this week: water meters for buildings 1, 2, and 5; electrical meters for buildings 1, 2, 3, 4, 5, 6, 7, 11, 18, 19, 24, 25, 26, and 27. Main building isolation valve replacements this week: domestic cold water in buildings 4, 5, and 6. In addition, eight water main valves were replaced. Contact Angela Fazio, 463-3428.

PROJECT 453 SEWER PIPE REPLACEMENT
The broken pipe in lagoon 2 is repaired and S2 Mechanical is waiting for a valve that has been ordered to complete the project. The gate valve is scheduled to be replaced August 31. Contact Mark Richardson, 463-3426.

PROJECT 454 BUILDINGS 4 AND 5 REROOF
The lower part of building 5 is complete and Umpqua Roofing is schedule to complete the upper part of building 5 on September 3. Skylights may be installed in October due to problems with the supplier. Contact Mark Richardson, 463-3426.

PROJECT 455 RESTROOM UPGRADES
Building 4 first floor restrooms punchlist to be complete August 28. Building 4 second floor restrooms paint, HVAC, ceiling grids and lights complete. Tile will be installed and allow to cure over the next two weeks with an anticipated completion of September 18. Building 6 lower level restrooms HVAC, electrical and ceiling installation is complete and workers will complete plumbing and install partitions and hardware over the next week. A new door is scheduled for September 3 and the restroom is scheduled to be turned over for use September 10. Contact Angela Fazio, 463-3428.

PROJECT 456 & 457 CLASSROOM UPGRADES
Crews are currently working to completed classrooms in the Center building and Building 19. Classrooms 453, 455, 456, 429, and 431 will be painted this week and are the last rooms in the Center building that will be painted. The classrooms are running a tight schedule but the rooms are expected to be completed by the fall term. Contact Mark Richardson, 463-3426.

PROJECT 459 SHOWER UPGRADES
Sections of women's east locker areas are ready to be turned over for use. Plumbing, electrical and cleaning to be complete next week for turnover Phase 3 scheduled for August 28. Tile installation is ongoing in the final men's area. Contractors will start demolition of final women's area on Monday, August 24. Anticipated substantial completion of entire locker room upgrade project is September 18. Contact Angela Fazio, 463-3428.

August 18, 2009
PROJECT 445 WEST ENTRANCE

The project is nearing completion with irrigation and landscaping being installed. Grab rails will be installed by August 21. The solid panel guard rail system will be installed mid-September. The entire project will be completed before fall term. Contact Todd Smith, 463-5132.

PROJECT 446 EXTERIOR LIGHTING
Christenson Electric continued to place path lighting fixtures (pole mounted and bollard) along egress paths around campus especially around Bristow Square. Parking lot fixtures are expected to be received in September and installed by the start of fall term. Contact Dave Smith, 463-3433.

PROJECT 447 CARPET REPLACEMENT/FLOOR COVERING
Rubinstein’s Contract Carpet is scheduled to install carpet in six classrooms in the Center building and 10 other classrooms on campus the week of August 17-21. Building 19 is scheduled to have new carpet installed in the hallways and several rooms starting Monday, August 17. Contact Mark Richardson, 463-3426.

PROJECT 448 KEYLESS ACCESS
Work continues on the keyless access project. The first system to be installed and commissioned will be the Proximity Card system associated with the Center building north elevator replacement. The proximity card will allow access to the Titan Store storage area on the first floor. Contact Dave Smith, 463-3433.

PROJECT 449 ASBESTOS ABATEMENT
Final abatement activities will be completed in the underground tunnel this week. Pacific Environmental is scheduled to be completed with their work mid-September but re-insulating piping will continue for a few months. Contact Mark Richardson, 463-3426.

PROJECT 450 EMERGENCY COMMUNICATION SYSTEM
SecureCom, the fire alarm contractor will be working during evening hours in building 19 August 17-21 to avoid disruption of the building occupants. Contact Dave Smith, 463-3433.

PROJECT 451 UTILITY SUBMETERING
The following meter installations were completed this week: water, buildings 4, 17, 18, and 19; natural gas, building 19. Main isolation valve replacements this week: domestic cold water, buildings 2, 3, 18, and 19. Contact Angela Fazio, 463-3428.

PROJECT 453 SEWER PIPE REPLACEMENT
A broken sewer pipe in lagoon 2 is now repaired. The contractor is expected to start installation of grease traps for the Center building kitchens this week. Contact Mark Richardson, 463-3426.

PROJECT 454 BUILDINGS 4 AND 5 REROOF
Metal roofing on building 5 is on schedule and expected to be completed mid-September. Skylights located in the open area between buildings 4 and 5 have been delayed but the contractor is working with the subcontractor to install the skylights by September 15. Contact Mark Richardson, 463-3426.

PROJECT 455 RESTROOM UPGRADES
Building 4 first floor restrooms punch list work is ongoing with an anticipated completion date of August 28. Building 5 second floor restrooms rough-in inspections are complete and drywall installed. August 17 to September 18 contractors will paint and install HVAC, ceiling grids and lights. Building 6 level 1 restrooms tile installation is complete. August 17-21 plumbing, HVAC, electrical and ceiling installation will be completed. The restroom is expected to be opened after a new door is installed September 15. Contact Angela Fazio, 463-3428.

PROJECT 456 & 457 CLASSROOM UPGRADES
Classroom upgrades are on an accelerated schedule to have classrooms ready for fall term. Most of the rooms have been upgraded with freshly painted walls and new carpet and lighting. Seven new podiums per week are arriving and being stalled in classrooms by Information Technology staff. Building 4 classrooms are on a fast track schedule with six deferred maintenance staff working 50 hours a week to make sure the classrooms are completed. Wallboard will be installed August 14-21. Door and ceiling installation and painting is expected to start August 24. Occupants on the second floor may experience odors from this construction activity. Contact Mark Richardson, 463-3426.

PROJECT 459 SHOWER UPGRADES
Men's SW and SE restrooms, shower 1 and 3, and the men's staff room have been opened for use. Building inspection, tile and ceiling is complete in the women's east locker areas. Plumbing and cleaning is to be completed August 17-20 with the Phase 3 area opened on August 20. Demolition has started in the final men's shower area. Anticipated completion is September 25 for the entire locker room upgrade project. Contact Angela Fazio, 463-3428.

August 17, 2009
PROJECT 445 STAIR AND HANDRAIL RENOVATIONS

Stairs in parking lot L, stairs leading to building 19 and stairs in building 4 are completed, except for handrail installation. Rails for the parking lot should be delivered within the next week. Contact Brian McMurray, 463-5829.

PROJECT 445 CENTER BUILDING NORTH ELEVATOR MODERNIZATION
Work is expected to be complete on the north elevator by the end of this month. Alternative access to the TitanStore is being provided on the south elevator. Contact Brian McMurray, 463-5829.

PROJECT 446 EXTERIOR LIGHTING
Christensen Electric, the contractor for the exterior lighting replacement, has begun to install pathway lighting on the south side of the campus, west of building 16. The pathway lighting is designed to provide a relatively high level of light on the campus paths with pole mounted fixtures while providing a visual indication of egress paths via the bollard fixtures. The parking lot lighting will also be replaced beginning in September. The new fixtures are LED based and provide a bright white light. Contact Dave Smith, 463-3433.

PROJECT 447 CARPET REPLACEMENT/FLOOR COVERING
Carpet replacement was scheduled to start this week and is looking like an aggressive schedule for the month of August. A carpet replacement schedule has been given to the LCC scheduling office. Contact Mark Richardson, 463-3426.

PROJECT 448 KEYLESS ACCESS
Allied Fire & Security continued work in building 1 Student Services, building 9 Auto/Diesel and Child Care buildings 24-26. Meetings with individual departments will continue for several weeks until all the campus buildings have been reviewed and requirements established. Contact Dave Smith, 463-3433.

PROJECT 449 ASBESTOS ABATEMENT
The abatement contractor is 90 percent complete with removing the material in the tunnel expected to contain asbestos. Abatement activities are scheduled to continue until the middle of September. Currently about half the buildings on the campus are scheduled to have the HVAC system shut down so Pacific Environmental can remove some suspicious materials that has been located in areas of the building. Contact Mark Richardson, 463-3426.

PROJECT 450 EMERGENCY COMMUNICATION SYSTEM
SecureCom, the fire alarm contractor, is installing new speakers, annunciators, and wiring for the upgraded fire alarm systems and deferred maintenance staff are installing wiring and conduit. This project will include public address speakers in most spaces for the mass communication system. Contact Dave Smith, 463-3433.

PROJECT 451 UTILITY SUBMETERING
EMK has been working aggressively on installing gas and water meters on campus. Most of the irrigation meters and some meters in the tunnel have been installed. Due to late material shipments, the shutdown schedule for buildings 1, 2 and the Center building will be revised. A modified schedule will be sent later this week. Contact Mark Richardson, 463-3426.

PROJECT 452 ELECTRICAL UPGRADES
Replacement of old and obsolete electrical panels by LCC deferred maintenance electricians is on hold while more time critical projects such as classroom upgrades are being completed. It is anticipated the panel replacements will resume during the shutdown August 22-23 and then again after the beginning of classes in September. An electrical transformer serving building 1 has been found to contain high levels of gases due to an internal arcing condition. It is of concern to campus Facilities personnel and every effort is being made to replace this transformer with a new unit during the August shutdown. The transformer does not present an electrical shock hazard to building occupants. Contact Dave Smith, 463-3433.

PROJECT 453 SEWER PIPE REPLACEMENT
The broken pipes and modifications for the lagoons are scheduled to start this week. The grease traps are on order and installation is schedule to start the week of August 17. Contact Mark Richardson, 463-3426.

PROJECT 454 BUILDINGS 4 AND 5 REROOF
New access ladders will be installed after the metal roofing on the outside of building 5 and cap metal flashing is complete. The skylight contractor is scheduled to be on site the week of August 10 and a pre-installation meeting will be held to plan for working over an area that is expected to have a lot of pedestrian traffic. The project is on schedule to be completed in mid September. Contact Mark Richardson, 463-3426.

PROJECT 455 RESTROOM UPGRADES
Punchlist work is ongoing in building 4 first floor restrooms. Building 5 second floor restrooms mortar bed replacement is complete; framing, plumbing rough-in complete; and electrical rough-in is ongoing. Building 6 lower level restrooms tile installation is ongoing. Contact Angela Fazio, 463-3428.

PROJECT 456 & 457 CLASSROOM UPGRADES
Seven podiums per week are starting to arrive on site for installation. Deferred maintenance staff is completing final touches on several rooms to prepare for carpet installation. This is the final step before the electronics are installed completing the smart classroom upgrades. The schedule for activities in August is aggressive and is expected to cause a lot of dust and noise. Contact Mark Richardson, 463-3426.

PROJECT 458 RTS AND BUILDING 12 PAINT BOOTHS
Building 12 is being prepared for installation of a new paint booth which is scheduled to arrive this week, with installation scheduled to begin in two weeks. Contact Brian McMurray, 463-5829.

PROJECT 459 SHOWER UPGRADES
Building inspection is complete in men's locker room areas: southwest and southeast restrooms, shower #1 and #3, and men's staff room. All of these areas will be available for use next week. Women's locker east areas are being retiled and the ceiling is to be installed in these areas next week. Electrical bids are due next week for installation of hand dryers, hard-wired sinks and new sealed light fixtures. Contact Angela Fazio, 463-3428.

August 10, 2009
PROJECT 445 STAIR AND HANDRAIL RENOVATIONS

Stairs in parking lot L, stairs leading to Building 19 and stairs in Building 4 are completed except for handrail installation. Rails for the parking lot should be delivered within the next two weeks. Contact Brian McMurray, 463-5829.

PROJECT 445 CENTER BUILDING NORTH ELEVATOR MODERNIZATION
Work continues on the north elevator modernization. New car doors and hoistway doors have been installed. Work will begin on car and hall call-panels this week. Alternative access to the Bookstore is being provided on the south elevator. Contact Brian McMurray, 463-5829.

PROJECT 446 EXTERIOR LIGHTING
Christensen Electric, the contractor for the exterior lighting replacement, continues to auger four foot deep holes for the pathway pole and bollard bases this week. 20% of the wall pack LED fixtures are installed. Look at the lower levels of buildings 15 and 17 to find them. 90% of the Cree LED soffit lights have been installed, with building 4 waiting at this point due to construction schedules. The rest of the LED fixtures to be installed are shipping this week, with installation to follow as schedules permit. Contact Dave Smith, 463-3433.

PROJECT 447 CARPET REPLACEMENT/FLOOR COVERING
New flooring for Building 12 classrooms and offices is now complete. Carpet was installed Monday, July 27 in Center fourth floor classrooms 416, 426 and 432. Contact Mark Richardson, 463-3426.

PROJECT 448 KEYLESS ACCESS
Allied Fire & Security continued work in Building 1 Student Services, Building 8 Welding, and Building 4 Health. Dave Smith, the project coordinator, met with representatives of Building 1 to discuss their requirements for access and gave a presentation of the system to public safety. Meetings will continue until all the campus buildings have been reviewed and requirements established. Electricians are installing conduit in multiple buildings on campus. 25% of the infrastructure is complete. Contact Dave Smith, 463-3433.

PROJECT 449 ASBESTOS ABATEMENT
Asbestos removal inside the tunnel is on schedule. The deferred maintenance crews working on insulating the pipes in the tunnel have temporarily been reassigned to help finish the smart classrooms. On August 7 Buildings 17 and 18 will have the HVAC system shut down to allow the contractor to remove asbestos fittings. Contact Mark Richardson, 463-3426.

PROJECT 450 EMERGENCY COMMUNICATION SYSTEM
SecureCom, the fire alarm contractor, is installing new speakers, annunciators, and wiring for the upgraded fire alarm systems. LCC deferred maintenance employees have begun the installation of the wiring and conduit for this project. Contact Dave Smith, 463-3433.

PROJECT 451 UTILITY SUBMETERING
EMK is currently working on installing irrigation meters throughout the campus. On August 7, water and gas services will be shut off. for Buildings 3, 9, 15, and 16. Power will be shut down on August 7 from 7:00 a.m. – 7:00 p.m. in Buildings 1, 2 and Center. Contact Mark Richardson, 463-3426.

PROJECT 452 ELECTRICAL UPGRADES
LCC deferred maintenance electricians have been replacing up to 43 obsolete and unsafe electrical panels at the main campus. Work will continue to replace 30 additional panels in Buildings 4, 5, 11, and 12 in future weeks through the summer. 65% of the backbone conduit and control panel boxes are installed, buildings 9, 24, 12 (except for the paint booth), and 13. Panel upgrades are on hold for now due to class room schedules. Building 7 is complete, Building 4 is 75% complete. Buildings 11 and 5 are on order and we may change them out on August 22nd and 23rd. Departments effected by this work will be notified in advance in accordance with College policy.
Contact Dave Smith, 463-3433.

PROJECT 453 SEWER PIPE REPLACEMENT
The sewer pipe replacement in the lagoon is schedule to start within the next two weeks. Grease trap installation will start this week and is expected to last two to three weeks. Deferred maintenance staff will place warning notices at locations affected by installation. Installation of grease traps is not expected to interrupt kitchen service. Contact Mark Richardson, 463-3426.

PROJECT 454 BUILDINGS 4 AND 5 REROOF
Umpqua Roofing has completed the flat roof section of building 5 and Steadman Sheet Metal, a subcontractor to Umpqua Roofing, is completing the new metal roofing around the perimeter. Skylights for building 5 are expected to arrive the week of August 10. This activity is expected to be loud and dusty in that general area and installation will take 2 days. The area under the roof will be sectioned off to keep the staff and students safe from overhead work. Contact Mark Richardson, 463-3426.

PROJECT 456 CLASSROOM UPGRADES
Deferred maintenance crews are installing the remaining white boards this week. Work in building 15 rooms 206 and 208 will be completed by August 28. Light fixtures are beginning to be installed in building 12. Painting is being done with low VOC paint and some classrooms might have odors for a few days after being painted. Carpet being installed in the classrooms is made of recycled materials and is installed without glue. In building 4, framing and rough-in electrical for the interior wall is complete and a section of floor will be filled with concrete on August 3. Framing and block work has started at the new classroom entrances. Expect noise the week of August 10 during the masonry work. Contact Mark Richardson, 463-3426.

PROJECT 457 SMART CLASSROOM INFRASTRUCTURE
Several of the classroom projects are almost ready for the electronic installations, finalizing the smart classroom upgrades. The first shipment of podiums will be installed in buildings 6, 12, 16, and the Center building. Another shipment is expected the week of August 3. Contact Mark Richardson, 463-3426.

PROJECT 458 RTS AND BUILDING 12 PAINT BOOTHS
Concrete demolition for new paint booth installation in building 12 will start Tuesday, August 4. Booth installation is scheduled to begin August 17 and should take one week. Contact Brian McMurray, 463-5829.

July 28, 2009
Sustainability in Deferred Maintenance Restroom Upgrades
Lane is working to incorporate sustainable practices into all of the deferred maintenance projects.  The restroom upgrades in Buildings 4, 5, and 6 involve replacing old toilets that used 3.5 gallons per flush with new auto-flushing dual flush toilets.  These toilets automatically flush either 1.1 gallons or 1.6 gallons.  The replacement of 45 toilets in these three buildings will result in approximately 130,000 gallons of water saved per year.  Saving water saves the college money and helps preserve habitat in and around the McKenzie River. Contact Jennifer Hayward, 463-5594.

445 Stair and Handrail Renovations
Remaining concrete steps in parking lot ‘L, and steps leading to bldg 19 will be poured on Friday, July 24. Installation of handrails remains. Completion of painting and handrail installation remains to be done on Building 4 steps. Contact Brian McMurray, 463-5829.

445 Center Bldg North Elevator Modernization
Work continues on north elevator modernization. Alternative access to the Bookstore is being provided on the south elevator. Contact Brian McMurray, 463-5829.

Project 446 Exterior Lighting
Christensen Electric, the contractor for the exterior lighting replacement, is augering holes for the pathway pole and bollard bases this week. The excavating auger creates a four foot deep hole in which either a precast or a poured concrete base will be installed. Holes are filled immediately or plywood covers placed over them if left unfilled overnight. They are working closely with LCC Groundskeeping to ensure that there is minimal damage to landscaping. Contact Dave Smith at 463-3433.

Project 448 Keyless Access Project
Allied Fire & Security continued work in Student Services, Auto/Diesel, and Child Care. Meetings with individual departments will continue for several weeks until all the campus buildings have been reviewed and requirements established. Contact Dave Smith at 463-3433.

Project 450 Emergency Communication System
SecureCom, the fire alarm contractor, is installing new speakers, annunciators, and wiring for the upgraded fire alarm systems. This project will include public address speakers in most spaces for the Mass Communication system. LCC deferred maintenance employees have begun the installation of the wiring and conduit for this project. Contact Dave Smith at 463-3433.

Project 452 Electrical Upgrades
LCC deferred maintenance electricians have been replacing up to 43 obsolete and unsafe electrical panels at the main campus. Work will continue to replace 30 additional panels in Buildings 4, 5, 11, and 12 in future weeks through the summer. Departments effected by this work will be notified in advance in accordance with College policy. Contact Dave Smith at 463-3433.

Project 455 Restroom Remodels
Building 4 1st Floor Restrooms exterior doors replaced; punchlist item work ongoing. Building 5 2nd Floor Restrooms demolition complete, plumbing rough-in in progress. Framing on hold awaiting decision on replacement of mortar bed. Building 6 Level 1 Restrooms rough-in complete; framing and drywall complete. Design changes to install Men's room door complete. Contact Angela Fazio, 463-3428.

458 RTS and Bldg 12 Paint Booths
Demolition of existing paint booth in building 12 will be completed Friday, July 24. New booth for bldg 12 will ship by July 31. Contact Brian McMurray, 463-5829.

Project 459 Shower Upgrades
Currently out of service for tile replacement: East half of Women's Locker Area. Currently out of service for fixture replacement: Men's Shower Stall #3, Men's West Restroom, Women's Staff and Men's Staff. To be turned over for use next week: Men's East Restroom, Men's Shower Stall #1. Dropped ceiling and duct extension installation to continue, sprinkler head replacement next week. Partitions 2 weeks out, lights 5 weeks out. Contact Angela Fazio, 463-3428.


July 21, 2009
SUSTAINABILITY UPDATE - SOLAR THERMAL PROJECT
A multiple-building solar thermal project is currently in the design phase. This is a unique and innovative project that includes funding from the Health and Wellness Building, Deferred Maintenance, and the Bond. The project involves installing solar thermal panels on the new Health and Wellness Building. These panels will heat water that will be used in the Laundry, the Health and Wellness Building, and Building 5. Since hot water needs and production can vary from day to day and term to term, any excess hot water produced by the panels will feed into the college's central heating system. This renewable energy project will reduce the college's natural gas costs and carbon emissions associated with natural gas use. Contact: Jennifer Hayward, 5594.

PROJECT 445 STAIR AND HANDRAIL RENOVATIONS
Remaining concrete steps in parking lot ‘L’ will be poured this week. Installation of handrails remains. Long set of steps leading from ‘L’ to building 19 have been removed and new steps are scheduled to be poured on July 27. Metal stair frame in building 4 has been installed and step treads have been poured. Painting and handrail installation remain. Contact Brian McMurray, 463-5829.

PROJECT 445 CENTER BUILDING NORTH ELEVATOR MODERNIZATION
NW Elevator continues to make good progress on north elevator modernization. Alternative access to Bookstore is being provided on the south elevator. Contact Brian McMurray, 463-5829.

PROJECT 446 EXTERIOR LIGHTING
Christensen Electric, the contractor for the exterior lighting replacement, is excavating the pathway pole and bollard bases this week. The excavating auger will create a 3 to 5 foot deep hole in which either a precast or a poured concrete base will be installed. Holes will be filled immediately or plywood covers placed over them if left unfilled overnight. The contractor is working closely with LCC grounds staff to ensure minimal damage to landscaping. Contact Dave Smith, 463-3433.

PROJECT 447 CARPET REPLACEMENT/FLOOR COVERING
Carpet and linoleum installation in four classrooms in building 12 is expected to be completed the week of July 20. Next, carpet will be installed in classrooms on the Center fourth floor. Carpet replacement is also scheduled for building 6 rooms 140 and 126 the week of July 27. Beginning the second week of August, another large shipment of carpet will be delivered for buildings 19, 3, and 15 and Florence. Contact Mark Richardson, 463-3426.

PROJECT 448 KEYLESS ACCESS PROJECT
Allied Fire & Security are continuing work in Student Services, Auto/Diesel, and Child Care. Meetings with individual departments will continue for several weeks until all the campus buildings have been reviewed and requirements established. Contact Dave Smith, 463-3433.

PROJECT 449 ASBESTOS ABATEMENT
Pacific Environmental is scheduled to complete work in the last section of tunnel by July 28. Asbestos removal in the boiler room of building 11 is completed and work started Friday, July 17 in buildings 17, 15 and 12. Abatement crews are scheduled to start July 20 to remove the ceiling area around the old paint booth in building 12 to clear the path for installation of the new paint booth. Contact Mark Richardson, 463-3426.

PROJECT 450 EMERGENCY COMMUNICATION SYSTEM
SecureCom, the fire alarm contractor, is installing new speakers, annunciators and wiring for the upgraded fire alarm systems. This project will include public address speakers in most spaces for the mass communication system. LCC deferred maintenance employees have begun the installation of the wiring and conduit for this project. Contact Dave Smith, 463-3433.

PROJECT 451 UTILITY SUBMETERING
EMK/JKG has been installing irrigation meters around the project site and is expecting to complete more over the next two weeks. No shutdowns are scheduled for July 24-25 during the Relay for Life event. Contact Mark Richardson, 463-3426.

PROJECT 452 ELECTRICAL UPGRADES
LCC deferred maintenance electricians continue to replace up to 43 obsolete and unsafe electrical panels at the main campus including 30 additional panels in buildings 4, 5, 11, and 12 during the summer. Departments effected by this work will be notified in advance in accordance with college policy. The piping for the renewable energy project was insulated which concludes the first phase of the project. LCC Facilities staff will meet with Evergreen Engineering later this month to discuss the campus electrical systems one line verification and update, arc flash studies, and overcurrent coordination studies. Contact Dave Smith, 463-3433.

PROJECT 453 SEWER PIPE REPLACEMENT
EMK will be installing the grease traps in the kitchen area of the Center building starting July 28. This work will be done after regular business hours and no impact on classes or other scheduled activities is expected. Other arrangements will be made for the work if the contractor expects problems that will take that area out of service. Contact Mark Richardson, 463-3426.

PROJECT 454 BUILDING 4 and 5 REROOF
Umpqua Roofing has completed removing the old roofing materials and should complete installation of single ply roofing over the gymnasium by Wednesday, July 22. Stedman Sheet Metal is currently installing new metal roofing on the east side and tower of building 5 and should complete work in two weeks. The scaffolding currently in place on the south side of building 5 will remain in place for safe access to install new metal roofing along the south side of the building. Contact Mark Richardson, 463-3426.

PROJECT 456 CLASSROOM UPGRADES
Currently 26 classrooms are being upgraded to smart classrooms with more starting August 1. Third Generation Painting has completed many of the classrooms and will start painting walls in buildings 8 and 9. Deferred maintenance crews will be patching concrete floors and walls in building 8 rooms 110 and 122 and patching walls and running electrical in Center building rooms 416, 427 and 432. Rooms that have been painted and will have podiums, whiteboards and new carpet installed over the next three weeks are Center building rooms 401, 402, 416, 423, 425, and 427, and building 16 rooms 126, 140, 161 and 271. Deferred maintenance crews will begin work on building 15 rooms 206 and 208 and building 19 rooms 109, 203 and 132 next. In the building 4 first floor classrooms, demolition is complete and deferred maintenance crews have been modifying the electrical system and installing new walls. The HVAC contractor will be on site laying out the new system for the classrooms and modifying the existing system starting the week of July 20. Eugene Mirror and Glass is scheduled to begin installation of the store front system the week of August 12. Contact Mark Richardson, 463-3426.

PROJECT 458 RTS AND BUILDING 12 PAINT BOOTHS
Orders have been placed for new paint booths for building 12 and the RTS building at the airport. Demolition of old booth in building 12 is underway. Contact Brian McMurray, 463-5829.

July 14, 2009
PROJECT 445 STAIR AND HANDRAIL RENOVATIONS
Work continues on steps in parking lot L this week. Expect the last steps to be poured on July 20. The long set of steps leading from parking lot L to building 19 have been removed and new steps should be poured on July 27. Metal stair frame in building 4 has been installed and the first pour for step treads will be July 13. Contact Brian McMurray, 463-5829.

PROJECT 445 CENTER BUILDING NORTH ELEVATOR IMPROVEMENT
New doors should be installed by July 17. A new motor and controller are installed and brake work is almost complete. Alternative access to the bookstore is being provided on the south elevator. Contact Brian McMurray, 463-5829.

PROJECT 446 EXTERIOR LIGHTING
Christensen Electric, the contractor for the exterior lighting replacement, will be excavating for the pathway pole and bollard bases next week. The excavating auger will create a 3 to 5 foot deep hole in which either a precast or a poured concrete base will be installed. Holes will be filled immediately or plywood covers placed over them if left unfilled overnight. They are working closely with LCC Groundskeeping to ensure that there is minimal damage to landscaping. LCC deferred maintenance electricians continue to work to replace old light fixtures that are mounted to the perimeters of the campus buildings with high efficiency LED light fixtures. They are approximately twenty-five percent complete with the work. Contact Dave Smith, 463-3433.

PROJECT 447 CARPET REPLACEMENT/FLOOR COVERING
Carpet replacement for Building 12 upper floor classrooms and offices is scheduled to start on July 13 and complete about July 27. The next shipment of carpet is scheduled to be installed in some of the classrooms in the Center building and Building 16. A large order of carpet is expected to arrive the first week of August and that order is for the remaining smart classrooms. Contact Mark Richardson, 463-3426.

PROJECT 448 KEYLESS ACCESS PROJECT
Allied Fire & Security began work in Building 1 Student Services, Building 9 Auto/Diesel, and Buildings 24-27 Child Care. A presentation was given to the Executive Team on July 9 to review the keyless access system planned for the campus. Much valuable guidance was received from this committee on policy related questions. Meetings with individual departments will continue for several weeks until all the campus buildings have been reviewed and requirements established. Contact Dave Smith, 463-3433.

PROJECT 449 ASBESTOS ABATEMENT
Pacific Environmental has now completed 80 percent of the tunnel work along with other various locations in other buildings. Every Friday beginning from July 10 the HVAC units will be turned off at different locations allowing the contractor to perform their abatement activities. Most areas can be completed in one day. Contact Mark Richardson, 463-3426.

PROJECT 450 EMERGENCY COMMUNICATION SYSTEM
SecureCom, the fire alarm contractor, is installing new speakers, annunciators, and wiring for the upgraded fire alarm systems. This project will include public address speakers in most spaces for the mass communication system. LCC deferred maintenance employees have begun the installation of the wiring and conduit for this project. Contact Dave Smith, 463-3433.

PROJECT 451 UTILITY SUBMETERING
EMK/JKG is on site doing preparation work for installing the meters. The first scheduled shutdown for meter installation is July 17 for Buildings 6, 7, and 9. During the shut down there will be no water or gas service to these building for the major part of the day. The laundry facilities will be shut down at a different time and day to avoid any interruptions in services to the campus. Contact Mark Richardson, 463-3426.

PROJECT 452 ELECTRICAL UPGRADES
LCC deferred maintenance electricians have been replacing up to 43 obsolete and unsafe electrical panels at the main campus and completed eight panels in Building 7. Work will continue to replace 30 additional panels in Buildings 4, 5, 11, and 12 through the summer. Departments affected by this work will be notified in advance in accordance with college policy. Twin Rivers Plumbing contractors finished piping work last week in the tunnel system and in building 7 for a renewable energy project. Evergreen Engineering has finished the Campus Electrical Systems one line verification and update, Arc Flash studies, and overcurrent coordination studies and submitted plans and recommendations. Contact Dave Smith, 463-3433.

PROJECT 453 SEWER PIPE REPLACEMENT
Grease traps for the Center kitchen have been ordered and installation is expected to start the week of July 20. Grease traps in the kitchen area are needed to avoid clogging the drains with grease and will be easy to maintain by facilities staff. Contact Mark Richardson, 463-3426.

PROJECT 454 BUILDING 4 AND 5 REROOF
The flat roof work has started over the top of building 5 and should be completed by July 17. Umpqua Roofing has made adjustments in their schedule to accommodate activates taking place in that area. Contact Mark Richardson, 463-3426.

PROJECT 455 RESTROOM REMODELS
Remodel is complete in Building 4 first floor restrooms and the restrooms are open. Punchlist items are being addressed. Exterior doors scheduled to be replaced July 16-17 during which time restrooms will be out of service. Building 4 second floor restrooms demolition are ninety percent complete. Demolition in building 6 lower level restrooms is complete and framing, plumbing and electrical rough-in have started. Contact Angela Fazio, 463-3428.

PROJECT 456 CLASSROOM UPGRADES
Building 16 classrooms 161 and 271 are scheduled to be painted in the next two weeks. The first 10 smart classroom podiums are expected to be completed the week of July 20. A large order of carpet is expected to be shipped next week from the factory and should arrive on site the same week the first group of podiums is being installed. A smart classroom upgrade and flooring replacement will be done for a classroom at the Florence Center this summer also. All of the rooms are expected to be completed by September 1. Mark Richardson, 463-3426.

PROJECT 458 AMTF AND BUILDING 12 PAINT BOOTHS
New paint booths have been ordered for the return to service building at the airport and for Building 12. Demolition of the old booth in Building 12 is scheduled to begin July 13. Contact Brian McMurray, 463-5829.

PROJECT 459 SHOWER UPGRADES
Currently out of service for tile replacement: men's shower stall #3, men's west restroom. Currently out of service for fixture replacement and installation of ceiling: women's staff locker, men's staff locker, men's east restroom and men's shower stall #1. Fifty percent of fixture order arrived July 1 and the remainder is expected by July 17. Contact Angela Fazio, 463-3428.

July 7, 2009
PROJECT 446 EXTERIOR LIGHTING

Christensen Electric, the contractor for the exterior lighting replacement, has been working to ensure that the pole bases for the parking lot fixtures are ready to accept the new poles. The contractor will be pouring the bases for the pathway bollards (i.e. waist height poles) fixtures next week. Installation of pre-cast pathway light bases will also occur in the next month. The contractor is working closely with Groundskeeping to ensure that there is minimal damage to landscaping. Deferred maintenance electricians continue to work to replace old light fixtures that are mounted to the perimeters of the campus buildings with high efficiency LED light fixtures. Electrical service to the campus bus station was restored and the clock tower is working again. Work on this project is scheduled to be “substantially complete” by September 29, 2009. The upgrades to the campus lighting system were designed by Hanna Engineering of Eugene. Contact Dave Smith at 463-3433.

PROJECT 447 CARPET REPLACEMENT
Carpet replacement for Building 12 is scheduled to start on July 13, 2009 and is expected to take about two weeks to complete the upper floor offices and classrooms. The carpet contractor has measured for carpet replacement at the Florence campus and Building 19 so they can be added to the list of areas that need new carpet. The next shipment of carpet is schedule to arrive on site the third week of July and is scheduled to be installed in some of the classrooms in Center and Building 16. The large order of carpet is expected to arrive the first week of August and that order is for the remaining smart classrooms. Contact Mark Richardson at 463-3426.

PROJECT 448 "KEYLESS" DOOR ACCESS
Allied Fire & Security began work in Building 1, Student Services. Meetings will be established with Academic Deans and Departmental leadership to review the access controls planned for each building. These meetings will continue for several weeks until all the campus buildings have been reviewed and requirements established. Work on this project is scheduled to be “substantially complete” by December 31, 2009. Contact Dave Smith at 463-3433.

PROJECT 449 ASBESTOS ABATEMENT
Pacific Environmental has now completed 80% of the tunnel work along with other various locations in other buildings. Building 4 abatement activities took place this week and have been completed allowing construction to continue in that area. On Friday, July 10, 2009 Pacific Environmental will be working on removing the asbestos materials from each of the boiler rooms on campus. Every Friday from July 10, 2009 forward, the HVAC units will be turned off at different locations for abatement activities. Most all areas can be completed in one day. Center is scheduled to take two or three days and will be completed over a weekend when the campus is closed. Contact Mark Richardson at 463-3426.

PROJECT 450 EMERGENCY COMMUNICATION SYSTEM
SecureCom, the fire alarm contractor, is installing new speakers, annunciators, and wiring for the upgraded fire alarm systems. This project will include public address speakers in most spaces for the mass communication system. Deferred maintenance employees have begun the installation of the wiring and conduit for this project. They are currently working in Buildings 9 and 12. Work on this project is scheduled to be “substantially complete” by September 15, 2009. Contact Dave Smith at 463-3433.

PROJECT 451 UTILITY SUBMETERING
EMK/JKG is on site working in several locations completing some of the preparation work for installing the meters. All of the water and gas meters are on site. The first scheduled shutdown for meter installation is July 17, 2009. The buildings being affected are 6, 7, and 9. During the shut down, there will be no water or gas service to these buildings with the exception of the laundry facilities. The laundry facilities will be shut down at a different time and day to avoid any interruptions in services to the campus. Contact Mark Richardson at 463-3426.

PROJECT 452 ELECTRICAL UPGRADES
Deferred maintenance electricians have been replacing up to 43 obsolete and unsafe electrical panels at the main campus. Work was completed on all panels (a total of eight) in Building 7 this week. Work will continue to replace 30 additional panels in Buildings 4, 5, 11, and 12 in future weeks through the summer. Departments effected by this work will be notified in advance in accordance with college policy. Contact Dave Smith at 463-3433.

Twin River Plumbing finished piping work last week in the tunnel system and in Building 7 for a renewable energy project. A small leak was discovered in the new piping but was quickly repaired. The piping is being insulated this week. This concludes the first phase of the project. Contact Dave Smith at 463-3433.

Evergreen Engineering, a Eugene Electrical Engineering consultant, is close to finishing the Campus Electrical Systems one line verification and update, arc flash studies, and overcurrent coordination studies. They will be submitting their plans and recommendations in the next week. Contact Dave Smith at 463-3433.

PROJECT 453 SEWER PIPE REPLACEMENTS/GREASE TRAP INSTALLATIONS
The grease traps have been ordered and installation is expected to start the week of July 20, 2009. Individual grease traps will be installed in the kitchen area where needed to avoid clogging the drains with grease. The grease traps will be easy to clean by the Facilities staff making down time very minimal at each location. Contact Mark Richardson at 463-3426.

PROJECT 454 BUILDINGS 4 & 5 REROOFING
Stedman Sheet Metal is finishing up on the roof peeks of Building 4 and will be installing the cap flashing at the edge of the building by the end of the week. Once the cap flashing is installed the Building 4 roof replacement will be complete. The next task for Stedman Sheet Metal is to start installing metal roofing on the west side of Building 5. Umpqua Roofing has started to tear off the sloped side of Building 5 this week and is expected to have the tear-of work completed by July 8, 2009. The flat roof work has started over the top of the Building 5 gymnasiums. This work should be completed by the end of next week. This section of roof has no tear off of the old materials. Umpqua Roofing has made adjustments in their schedule to accommodate activities taking place in that area. Contact Mark Richardson at 463-3426.

PROJECT 455 RESTROOM REMODELS
The remodel is complete in Building 4 first floor restrooms. Temporary occupancy was approved on July 2, 2009 and the restrooms are now available for use. Exterior doors will be replaced on these restrooms within the next two weeks. This final work will not affect occupancy. Building 4 second floor restrooms will be out of service for demolition starting July 6, 2009. Demolition in Building 6 first floor restrooms is complete. Plumbing rough-in is ongoing. Contact Angela Fazio at 463-3428.

PROJECT 456 CLASSROOM UPGRADES
Deferred maintenance staff is working hard to make sure all the classrooms on the deferred list are completed by the fall term. Currently there are nineteen classrooms being upgraded to smart classrooms with more to start soon. The classrooms when finished will have new paint, carpet, podiums, and new lighting in most locations. Building 16 classrooms 161 and 271 are scheduled to be painted in the next couple of weeks. Currently, Building 12 classrooms 119a, 117, 214 and 216 have been painted and are ready for flooring on July 6. Center classrooms 401, 402, 423, and 425 are currently being painted and are expected to be completed on Friday July 3. The sample podium placed in Building 16 Room 271 will be removed on July 2, 2009. This podium model is expected to go into production July 6, 2009. The first ten podiums are expected to be completed the week of July 20, 2009. A large order of carpet is expected to be shipped next week from the factory and should arrive on site the same week the first group of podiums is being installed. The classrooms will get new carpet as the shipments arrive and will be determined by availability all of the rooms expected to be completed by September 1, 2009. Contact Mark Richardson at 463-3426.

PROJECT 459 SHOWER UPGRADES - BUILDING 5
The men's shower stall #3 and men's west restroom showers are currently out of service for tile replacement. The women's staff locker and men's stall locker are currently out of service for fixture replacement. The men's east restroom upgrade is complete and back in service. Contact Angela Fazio at 463-3428.

July 6, 2009
WEST CAMPUS ENTRANCE RE-ROUTED
Beginning Thursday, July 2, the main entrance walkway from parking lot B and the bus station into the campus will be blocked for pedestrian traffic. It will reopen Monday morning, July 6. Pedestrians will be rerouted toward building 1 Student Services and around the West Entrance Garden next to building 3 Administration into the main campus. Signs indicating alternate routes for people approaching the main entrance will be posted. The main entrance will be blocked due to excavation work needed for the new access ramps next to building 4. Contact Todd Smith, 463-5132.

June 30, 2009
PROJECT 446 EXTERIOR LIGHTING
Christensen Electric, the contractor for the exterior lighting replacement, has been installing underground conduits for electrical power for the new LED (Light Emitting Diode) lighting fixtures. They are working closely with LCC Groundskeeping to insure that there is minimal damage to landscaping, although some damage was accidently done to a natural planting area. LCC deferred maintenance electricians continue to work to replace old light fixtures that are mounted to the perimeters of the campus buildings with high efficiency LED light fixtures. Work on this project is scheduled to be “substantially complete” by September 29, 2009. The upgrades to the campus lighting system were designed by Hanna Engineering of Eugene. Contact Dave Smith at 463-3433.

PROJECT 448 "KEYLESS" DOOR ACCESS

A tentative schedule for Access Control implementation has been established on a building by building basis. Meetings with LCC Academic Deans and departmental leadership to review the access controls planned for each building will continue for several weeks until all the campus buildings have been reviewed and requirements established. The door hardware supplier, AMAG, met with the project consultants and with LCC IT staff to discuss database requirements for the Access Control system. Work on this project is scheduled to be “substantially complete” by December 31, 2009. Contact Dave Smith at 463-3433.

PROJECT 450 EMERGENCY COMMUNICATION SYSTEM
SecureCom, the fire alarm contractor, is installing new speakers, annunciators, and wiring for the upgraded fire alarm systems. This project will include public address speakers in most spaces for the Mass Communication system. LCC deferred maintenance employees have begun the installation of the wiring and conduit for this project. They are currently working in Buildings 9 and 12. Work on this project is scheduled to be “substantially complete” by September 15, 2009. Contact Dave Smith at 463-3433.

PROJECT 452 ELECTRICAL UPGRADES
LCC deferred maintenance electricians have been replacing up to 43 obsolete and unsafe electrical panels at the main campus. Work was completed on all panels (a total of eight) in Building 7 this week. Work will continue to replace 30 additional panels in Buildings 4, 5, 11, and 12 in future weeks through the summer. Departments effected by this work will be notified in advance in accordance with College policy. Contact Dave Smith at 463-3433.

Twin River Plumbing finished piping work in the tunnel system and in Building 7 for a renewable energy project.
The piping has successfully passed the Lane County inspection and will be insulated next week. This concludes the first phase of the project. Contact Dave Smith at 463-3433.

June 23, 2009
PROJECT 445 STAIR AND HANDRAIL RENOVATIONS

Replacement of connecting stairs in south parking lot L is continuing. The long set of steps leading from ‘L’ to building 19 have been removed. These stairs are scheduled to be completed by early August. Rumble strips have been created in designated parking lots and roads on the south and west sides of the campus. Stairs between buildings 4 and 5 are gone and new stairs should be installed by mid-August. Contact Brian McMurray, 463-5829.

PROJECT 445 CENTER BUILDING NORTH ELEVATOR MODERNIZATION
Reminder: North elevator will be shut down for the summer starting June 29. NW Elevator continues to assemble parts and equipment for the elevator upgrade. Those items will begin arriving on campus the week of June 22 and modernization work on the elevator will begin June 29. Alternative access to Bookstore will be provided. Contact Brian McMurray, 463-5829.

PROJECT 447 CARPET REPLACEMENT
Carpet has been ordered for a large numbers of rooms in buildings 11 and 12. The carpet order has suffered a minor set back due to a fire back East in a supply mill making it difficult to get all the carpet orders filled when promised. The offices and classrooms that are scheduled to receive new carpet will see some replacement starting at the end of July. Facilities will receive one order on June 25 and installation will be the following week. This shipment will cover the classrooms in building 12 and some other various locations. Contact Mark Richardson, 463-3426.

PROJECT 448 KEYLESS DOOR ACCESS
The Deferred Maintenance Leadership Team met with the access control consultants this week and meetings have been set with academic deans and departmental leadership to review the access controls planned for each building within their organization. Theses meetings will continue for several more weeks until all the campus buildings have been reviewed and requirements established. Installation of junction boxes for exterior doors continues in buildings 7, 9 and 12. Contact Dave Smith, 463-3433.

PROJECT 449 ASBESTOS ABATEMENT
Pacific Environmental has finished the area of tunnel between buildings 2 and 19. Their crews will be erecting a containment system starting at the location below the business building 2 and the administration building 3. Deferred maintenance crews completed installing insulation in the east and south sections of the tunnel. Abatement activities were completed in building 12 classrooms with PBS Environmental providing a clean air report on June 17. Contact Mark Richardson, 463-3426.

PROJECT 450 EMERGENCY COMMUNICATION SYSTEM
SecureCom, the fire alarm contractor, is installing new speakers, annunciators, and wiring for the upgraded fire alarm systems. Deferred maintenance employees have begun the installation of the wiring and conduit for this project in buildings 9 and 12. Contact Dave Smith, 463-3433.

PROJECT 451 UTILITY SUBMETERING
Contractors EMK and JKG have ordered part of the meters which are expected to be on site the end of June to kick off the installation activities. Contact Mark Richardson, 463-3426.

PROJECT 452 LAUNDRY UPGRADES
Twin River Plumbing continues to run piping in the tunnel system and in building 7 for a renewable energy project designed to recover heat from the laundry room driers and increase the efficiency of the laundry room boiler systems. Contact Dave Smith, 463-3433.

PROJECT 453 SEWER PIPE REPLACEMENTS
A design meeting was held on June 15 to discuss the location and sizes of the new grease traps for the Center kitchen. The new design should be completed by Monday June 22 and will enable LCC to move forward with ordering the appropriate sizes to avoid problems with the drain system in the future. Contact Mark Richardson, 463-3426.

PROJECT 454 BUILDINGS 4 & 5 REROOFING
Umpqua Roofing has completed the tear-off and reinstalled the flat roof section of building 4. Stedman Sheet Metal is currently working on installing the metal over the peeked roofs on building 4 and is expected to be completed with that area by Friday, June 26, completing the last roofing activity for building 4. Umpqua Roofing started the tear-off of the old roofing material a few days ago and is now currently working over the PE tower between the gymnasium and the fitness center. Weather permitting, removal of the old material on building 5 is expected to be completed June 26. Installation of the sheet metal roofing on building 5 is expected to start on June 29 and is scheduled to be completed by September 15. Contact Mark Richardson, 463-3426.

PROJECT 455 RESTROOM REMODELS
Work continues in building 4 first floor restrooms. Temporary occupancy is anticipated June 26. Demolition in building 6 level 1 restrooms to start June 22. Contact Angela Fazio, 463-3428.

PROJECT 456 CLASSROOM UPGRADES
Upgrades will start in Center 401, 402, 423, and 425 this week. Students and staff will begin to see sections of scaffolding setup in various locations around the stairs to the B
ookstore around June 23. This scaffolding is for access to run the wires for the new upgrades and is expected to be in place only two days. Contact Mark Richardson, 463-3426.

PROJECT 458 RTS AND BUILDING 12 PAINT BOOTHS
New paint booths for building 12 and the RTS building at the airport will be ordered this week. Contact Brian McMurray, 463-5829.

PROJECT 459 BUILDING 5 SHOWER UPGRADES
Currently out of service for tile replacement are the women's staff locker room, men's staff locker room, men's east water closet and shower bay #3. Tile work is completed in men's shower bay #1 and it is back in service. Contact Angela Fazio, 463-3428.

June 16, 2009

DEFERRED MAINTENANCE PROJECTS

Deferred maintenance project work continues at a rigorous pace with work accelerating into the early summer weeks. Here are some project specific highlights:

 

PROJECT 445 CENTER BUILDING NORTH ELEVATOR IMPROVEMENT

NW Elevator continues to acquire and fabricate equipment for the elevator upgrade. Parts and materials will begin arriving on campus the week of June 22. The elevator will be shut down for the summer, starting June 29. Alternative access to the Bookstore will be provided. Contact Brian McMurray, 463-5829.

 

PROJECT 445 STAIR AND HANDRAIL RENOVATIONS

Replacement of connecting stairs in south parking lot L is continuing. These stairs are scheduled to be completed by mid-July. "‘Rumble strips" in designated parking lots and roadways will be cut in this week. Stairs between buildings 4 and 5 have been removed and the contractor will pour concrete footings and floor patches Wednesday, June 17. Contact Brian McMurray, 463-5829.

 

PROJECT 448 KEYLESS DOOR ACCESS

The access control consultants and LCC project coordinator staff met with Child Care and Industrial Technology department leadership to review the access controls planned for buildings within their organization. These meetings will continue for several more weeks until all the campus buildings have been reviewed and requirements established. Contact Dave Smith, 463-3433.

 

PROJECT 452 ELECTRICAL UPGRADES

LCC deferred maintenance electricians replaced several breakers in building 7 and in Child Care buildings 24-27 during Saturday work. Panel replacement work will continue in Buildings 7 on subsequent Saturdays. Contact Dave Smith, 463-3433.

 

PROJECT 452 EXTERIOR LIGHTING

Christensen Electric, the contractor for the exterior lighting replacement, has been installing underground conduits for electrical power for the new lighting fixtures on main campus. They are working closely with LCC groundskeeping to insure that there is minimal damage to landscaping, although some damage was accidently done to a natural planting area. LCC deferred maintenance electricians continue to work to replace old light fixtures that are mounted to the perimeters of the campus buildings with high efficiency LED light fixtures. Contact Dave Smith, 463-3433.

 

PROJECT 454 BUILDING 4 AND 5 ROOF REPLACEMENTS

Umpqua roofing continues to strip off old roofing materials and is now installing 2 inches of additional closed cell insulation and either the metal standing seam roofing on the sloped roofs or a white TPO type single ply roofing on the flat roofs. This work is progressing nicely and is expected to be completed in late summer. Contact Mark Richardson, 463-3426.

 

PROJECT 458 AMTF AND BUILDING 12 PAINT BOOTHS

Proposals for new paint booths have been received and are being evaluated. Expect fabrication of booths to begin last week of June. Contact Brian McMurray, 463-5829.

June 12, 2009
EXTERIOR LIGHTING

Christensen Electric, the contractor for the exterior lighting replacement, has been installing underground conduits for electrical power for the new lighting fixtures. They are working closely with Groundskeeping to ensure minimal damage to landscaping. Some landscaping will be removed by Lane where new light poles are to be installed. Deferred maintenance electricians continue to work to replace old light fixtures that are mounted to the perimeters of the campus buildings with high efficiency LED light fixtures. Contact Dave Smith, 463-3433.

 

KEYLESS ACCESS SYSTEM

The Deferred Maintenance Leadership Team met with the access control consultants this week and meetings have been established with the LCC academic deans and departmental leadership to review the access controls planned for each building within their organization. These meetings will continue for several more weeks until all the campus buildings have been reviewed and requirements established. Contact Dave Smith, 463-3433.

 

EMERGENCY COMMUNICATION SYSTEM

SecureCom, the fire alarm contractor, is installing new speakers, annunciators and wiring for the upgraded fire alarm systems. This project will include public address speakers in most spaces for the Mass Communication system. Deferred maintenance staff have begun the installation of the wiring and conduit for this project in buildings 9 and 12. Contact Dave Smith, 463-3433.

 

ELECTRICAL UPGRADES

Twin River Plumbing continues to run piping in the tunnel system and in building 7 for a renewable energy project designed to recover heat from the laundry room driers and increase the efficiency of the laundry room boiler systems. Contact Dave Smith, 463-3433.

 

STAIR AND HANDRAIL RENOVATIONS

Replacement of connecting stairs in south parking lot L is continuing. These stairs are scheduled to be completed by mid-July. Demolition of the stairs between buildings 4 and 5 will occur June 6-7. Minor plumbing and footing work for the new stairs will occur in the lower level of building 4 the week of June 8. Contact Brian McMurray, 463-5829.

 

CENTER BUILDING NORTH ELEVATOR IMPROVEMENTS

Parts and materials for the elevator will begin arriving on campus the week of June 22. The elevator will be shut down for the summer beginning June 29. Contact Brian McMurray, 463-5829.

 

AMTF AND BUILDING 12 PAINT BOOTHS

Proposals for new paint booths were received this week from Rohner, the paint booth manufacturer and supplier for this project. Solarc Architecture and Engineering and Lane staff will be evaluating products for suitability for the respective programs. Fabrication of booths is expected to begin the last week of June. Contact Brian McMurray, 463-5829.

 

WEST ENTRANCE ADA RAMP UPGRADE

Site clearing for the west entrance is completed and underground plumbing has begun. Some over excavation had to be done to ensure the new access ramp on the southwest corner of building 4 was placed on solid ground. Contact Mark Richardson, 463-3426.

 

ASBESTOS ABATEMENT

Abatement activities are almost completed for the underground tunnel section. Pacific Environmental is expected to be complete work in the southwest area of the tunnel by June 11, then move to the area in the northeast corner of building 19, extending to the cross tunnel below building 2. An HVAC shut down is scheduled for completing the abatement work and is going to be performed on Fridays between June 26-September 4, except July 3, to minimize disruptions to summer activities. Insulation is being replaced by deferred maintenance staff. Contact Mark Richardson, 463-3426.

 

UTILITY SUBMETERS

Installations of the meters is scheduled to start late June or early July. A shut-down schedule is being developed for the installations. Contact Mark Richardson, 463-3426.

 

BUILDINGS 4 & 5 REROOF

Umpqua Roofing is removing the old composition roofing and installing new insulation and metal roofing on building 5. The metal roofing material is being loaded on the roof of building 5 by a crane service and is expected to continue the week of June 8. Flat roof work over building 4 will continue this week. Contact Mark Richardson, 463-3426.

 

CLASSROOM UPGRADES

Deferred maintenance staff are working in several locations in building 12 upgrading floor covering, ceiling tiles, and painting. Classrooms 214 and 216 are being upgraded with new carpet, paint, ceiling tiles, and lighting. On June 11 the upgrades for building 9 rooms 102 and 103 will start and is scheduled for completion September 15. June 13 will be the kick-off of summer classroom upgrades to smart rooms starting with rooms in buildings 6, 8, 12, and 15. Contact Mark Richardson, 463-3426.

June 5, 2009
445 West Entrance ADA Ramp Upgrades:
Site clearing for the west entrance is completed and underground plumbing has begun. Some over excavation had to be done to ensure the new access ramp on the south/West corner of building four as placed on solid ground.

449  Asbestos Abatement:
Abatement activities are almost completed for the underground tunnel section. Currently, Pacific Environmental group is working on the South/ West corner of the tunnel and is expected to be completed by June 11, 2009. The next section of tunnel that will be contained is located at the North/East corner of building 19 and the containment area will extend to the cross tunnel below building 2. An HVAC shut down is scheduled for completing the abetment work and is going to be preformed on Fridays starting June 26 and will continue until September 4, 2009. The only Friday not scheduled for a HVAC shut down is July 3, 2009. This will limit the amount of disruptions made to on going summer activities. Team Three members of the DM crew have been working on replacing the insulation in the tunnel and are currently working on the east side of the tunnel under building nine and working their way south towards building 16. Replacing the insulation is going well and should be completed in about 45 days.

451 Utility Sub Metering
EMK/JKG has completed the submittal process and will be ordering meters next week. Installations of the meters are scheduled to start at the end of June or the first part of July. A shut down schedule is currently being worked on and should be distributed by Friday June 12, 2009.

454 Buildings 4&5 Reroofing
Umpqua Roofing is currently working on the top of building #5 removing the old composition roofing and installing new insulation and metal roofing. Currently they have finished the west side and will be moving to the North side, weather permitting. Last week, construction activities shook loose a white power material from the underside of the roof in the gym and the material was tested by PBS. The material was found to contain nothing harmful to the students and staff.  New metal roofing showed up on site on Monday June 1, 2009 and installation started on Tuesday June 2, 2009. The metal roofing material is being loaded on the roof of building five by a crane service and is expected to continue the first part of next week. Flat roof work over building four has started and is expected to continue for a few more days. Currently, they are working over the walkway of building four.

456 Classroom Upgrades/457 Classroom Wiring
Currently, the DM team members are working in several locations in building twelve upgrading rooms, floor covering, ceiling tiles and paint. Classrooms 214 and 216 are being upgraded with new carpet, paint, ceiling tiles, and lighting. On June 11, 2009 the upgrades for rooms 9/102 and 9/103 will be started and is expected to be completed on or before September 15, 2009. One June 13, 2009 rooms 6/140, 6/126, 12,117, 8/122, 15/206 and many more will kick off the summer of classroom upgrades to smart rooms.

June 1, 2009
BUILDING 4 FIRST FLOOR RESTROOM UPGRADES

The first floor restrooms will continue to be out of service. Essex General Construction will have Acoella tile finish installing the wall and floor tile this week. The installation of the ceiling tile and fixtures will begin the week of June 1st.

BUILDING 5 SHOWER ROOMS TILE REPLACEMENT  

The far west rest room and first shower bay will be out of service until June. Eugene Tile and Marble will finish the installation of  tile the week of June 1st.  The installation of ceiling tile and fixtures will begin the week of June 1st.  No additional men's showers will be taken out of service until these restroom and shower areas are returned to service.  At the end of the week of June 1st, tile demolition will start in a portion of the women's staff locker room.

 

BUILDING 12 FLOOR COVERING REPLACEMENT

Flooring will be installed in Building 12 classrooms at the end of June. 

 

GREASE INTERCEPTOR FOR THE CENTER BUILDING KITCHEN

A grease interceptor is needed to catch the grease that would flow to the waste water treatment facility.  Grease adversely affects the operations of the waste water treatment facility by sticking to the biological colonies, resulting in reduced efficiencies of waste break down.  EMK mechanical contractors is completing a physical survey of the kitchen waste piping in the basement. There will not be any disruption of service until sometime during the Summer Break.  All shut-downs will be scheduled in advance with all of those potentially affected. 

May 27, 2009
DEFERRED MAINTENANCE ASBESTOS ABATEMENT

Pacific Environmental Group is ahead of schedule in removing asbestos but shut downs for short durations are needed to safely complete the work in tunnel boiler rooms. The schedule for shut downs will be complete May 29. Deferred maintenance workers will be reinsulating pipes over the next two months. Contact Mark Richardson, 3426.

 

DEFERRED MAINTENANCE BUILDING 4 REROOF

Umpqua Roofing began the flat roof May 26 with tear off and replacement of the flat roof and gutter system. Access to building 4 along the tennis court will remain closed until next year for work on the roof and the Health and Wellness building. Contact Mark Richardson, 3426.

 

DEFERRED MAINTENANCE CLASSROOM UPGRADES

Deferred maintenance crews are working on building 12, room 119A and building 15, room 206 and will start on rooms in building 12 the week of May 26. The work installing new flooring, painting, replacing ceiling tiles, and smart classroom wiring will take about three weeks. Contact Mark Richardson, 3426.

 

DEFERRED MAINTENANCE STAIR AND HANDRAIL RENOVATIONS

McKenzie Commercial began installing curbs in parking lot L south of building 16. Demolition of the steps between the upper and lower levels of building 4 and 5 will occur June 6 and 7. Contact Brian McMurray, 5829.

May 19, 2009
SUSTAINABILITY IN DEFERRED MAINTENANCE ELECTRICAL UPGRADES
As part of the deferred maintenance electrical upgrades, Lane will be replacing paper towel dispensers with electric hand dryers in several bathrooms. This upgrade will reduce the amount of trash that Lane sends to the landfill by up to 20 percent and will reduce the college's carbon footprint. One example of how this upgrade decreases the college's carbon footprint is elimination of all the diesel-fueled transportation that it takes to get the paper towels to campus. The college also anticipates saving about $100,000 per year in paper towel costs, waste disposal fees, and improvements in efficiency. More information on the costs of operating electric hand dryers vs. paper towel dispensers is available at www.lanecc.edu/sustainability/documents/handdryer.pdf. Contact Jennifer Hayward at (541) 463-5594.

DEFERRED MAINTENANCE BUILDINGS 4 and 5 RESTROOM UPGRADES
The first floor restrooms in building 4 will continue to be out of service. Essex General Construction began installing sheetrock and painting on May 18. Building 5 west toilet room and first shower bay will be out of service until June for installation of wall tile and shower drains. No other showers will be taken out of service until the first ones are complete. Contact Lance Greenley, (541) 463-3427.

DEFERRED MAINTENANCE WEST ENTRANCE ADA RAMP UPGRADE

Construction activities for the new west entrance began Monday, May 18. Demolition will last for five days and is expected to be very disruptive to staff at times. Deferred maintenance staff will be trained to help maintain safe passage for the pedestrian traffic and act as an information source to students trying to gain access to buildings 4 and 5. Contact Mark Richardson, (541) 463-3426.

DEFERRED MAINTENANCE BUILDING 4 REROOF
Umpqua Roofing is currently working on the top of building 4 removing the old composition roofing and installing new insulation and metal roofing. The new insulation will give better sound barrier for the offices below with providing better thermo protection from the weather changes. Access to building 4 along the tennis court has been closed for construction traffic only and will remain closed until next year. Access to the field is posted on sign boards and will be updated as work continues. Contact Mark Richardson, (541) 463-3426.

DEFERRED MAINTENANCE CLASSROOM UPGRADES
Building 16 rooms 161 and 271 are being upgraded to smart rooms with new wiring and painting. They should be back in service now. Room 119A in building 12 is the next room to be upgraded over the next three weeks. Contact: Facilities.

PARKING LOT L CONSTRUCTION WORK
Parking lot L, south of building 16 Science and Math, will have trucks and equipment blocking off areas as McKenzie Commercial works on replacing worn out steps. Signs directing pedestrians to use alternate drives are posted. Contact Brian McMurray, (541) 463-5829.

DEFERRED MAINTENANCE FIRE ALARM AND EMERGENCY COMMUNICATION UPGRADE
SecureCom, the fire alarm contractor, has begun to install new speaker/fire alarm annunciators that will allow the upgraded fire alarm systems to provide a pre-recorded voice message describing the emergency and providing instructions of what to do next. Deferred maintenance employees are currently installing wiring and conduit in building 9 (auto-diesel) which will take several weeks. All fire alarm devices are being recycled. When the work on campus is completed, the fire alarm systems will meet all current code and regulatory requirements for ADA and emergency communication. Contact Dave Smith, (541) 463-3433.

May 12, 2009
DEFERRED MAINTENANCE BUILDING 4 WORK

The west side building 4 access ramps and reconfiguration will continue with mobilization and demolition of this area. Demolition on the roof of building 4 is being done systematically and a new roof installed along the north side first. Noise and dust will be present as part of this work. Access to the lower level of building 4 will soon be re-routed along the north side of the building. Detour maps will be posted. Contact: Mark Richardson, project coordinator, (541) 463-3426.

DEFERRED MAINTENANCE PARKING LOT WORK
Parking lot L, south of building 16, will be closed May 16-17 for McKenzie Commercial Contractors, Inc. to begin demolition of connecting steps as part of the stair and handrail project. Work to replace the steps will take place following demolition and be completed about May 29. Users parked in the back of Lot L will need to follow signs directing them to the connecting drives between the rows for temporary pedestrian walkways. One set of stairs on the west side of the parking lot will be left in place because of the distance to the nearest drive from that end of the parking lot. Contact: Brian McMurray, project coordinator, (541) 463-5829.

May 5, 2009
LEGISLATORS INSPECT DEFERRED MAINTENANCE PROJECTS, MEET 50 NEW WORKERS
Contractors and LCC deferred maintenance employees began work on all of the projects the week of April 27. All of the projects have been awarded to the respective low quote contractors and quote results will be posted at: www.lanecc.edu/facilities/dm.

Oregon legislature members visit campusOn Saturday, May 2, several members of the Oregon legislature visited campus to view the progress of the deferred maintenance projects.

Extensive safety training for new employees is being provided.

A construction fence was erected west of building 4 in preparation for ADA ramp improvements.

Remodels continue on building 4 lower restrooms.

Materials and supplies are being ordered. Since many suppliers are not currently stocking much inventory, the lead times on materials and supplies seem to be longer than anticipated.

Construction drawings and specifications are being processed through the Lane County Planning department for building permits.

For more information contact Facilities Director David L. Willis, (541) 463-5566.

April 30, 2009
CENTER NORTH ELEVATOR TO BE CLOSED MONDAY, MAY 4, 6:00 A.M. to 9:00 A.M.
The Center building north elevator will be shut down from 6:00 a.m. to approximately 9:00 a.m. Monday, May 4. The elevator in the south end of the Center building on the first floor can be used to access the fourth floor. The elevator at Building 17 (Forum) can be used to access the Center second floor.  The shut-down is to allow Northwest Elevator Company to prepare for work to upgrade the elevator this summer as part of the Deferred Maintenance Stimulus.  Contact: Brian McMurray, project coordinator, at 5829 or Facilities at 5216.

April 28, 2009
WORK BEGINS: BUILDING 4 RESTROOMS CLOSED FOR REMODEL

A public quote opening for contractors was held Wednesday, April 15 on all of the deferred maintenance projects. The results will be posted on the deferred maintenance web site by Friday, May 1. Projects will be awarded to the apparent low bidders. Work is scheduled to begin on all projects this week.
Essex Construction began work April 27 on building 4 (Health) restrooms 142 and 144. The restrooms will be out of service until about June 5. Restrooms 266 and 267 off the PE lobby on the second floor will be available.
More than 25 new deferred maintenance trades employees started on April 27.
Comprehensive safety training for all deferred maintenance employees is being coordinated.
Contact: Dave Willis, (541) 463-5566.

April 14, 2009
BIDS DUE; HANDS-ON WORK TO BEGIN IN LATE APRIL

All design packages were completed on schedule and delivered to Lane Community College on Monday, April 6. Pre-bid meetings were held with all contractors on all of the projects. Approximately 55 contractors participated in the pre-bid meetings with another 10 to 15 contractors contacted to bid on smaller portions of the work.

It is the college’s intent to spread out the work, and create as many jobs as possible as quickly as possible while meeting extremely aggressive schedule constraints.

Bids are due Wednesday, April 15. All projects will be awarded as quickly as possible. Hands-on construction work will begin on all projects in April. In addition, Facilities, Management and Planning staff continue to work extremely long hours to directly hire 50-plus deferred maintenance project employees.

Materials are now beginning to be ordered. It appears that some of the lead times may be a challenge since many suppliers have very lean inventories.

Once contractors and employees are hired, parking challenges will become more pronounced on main campus. Facilities, Management and Planning staff are working to come up with parking alternatives.

The Deferred Maintenance Leadership Team will review the budgets and project costs once all the bids are turned in. For more information contact Dave Willis at (541) 463-5566.

SUSTAINABILITY GOALS INCLUDED IN DEFERRED MAINTENANCE WORK
Many of the projects that Lane Community College is doing as part of the Go Oregon stimulus plan will improve campus sustainability. One such project is the installation of building-level electricity, water and natural gas submeters. Submetering will help Facilities Management and Planning to better target and track energy and water conservation efforts. The submetering also will contribute to student learning in Lane's Energy Management and Water Conservation degree programs. For more information contact Anna Scott at (541) 463-5805.

photo of deferred maintenance staging areaMarch 20, 2009
Beginning Sunday, March 22, 2009, a portion of parking lot "N" on Lane's main campus will be use for deferred maintenance activities and will not be available for parking. Please see the site plans showing the parking spaces that will be affected:

March 24, 2009
GO OREGON DEFERRED MAINTENANCE UPDATE

Facilities Management and Planning staff continue to work almost exclusively on deferred maintenance Go Oregon stimulus funded projects. Nine engineering and architectural firms were hired to design various project scopes for permitting and coordination purposes. These designs will be completed for initial bidding on April 3. Many contractors and suppliers submitted templates with information to become qualified to participate during the bidding process. Bids on all work will be acquired April 6-10. All contracts should be awarded April 13-24. A fenced projects staging area will be set up in parking lot N during spring break. Project work has started and will pick up steam in April and May. Contact: Dave Willis, (541) 463-5566.

March 10, 2009
DEFERRED MAINTENANCE: GO OREGON PROJECTS UPDATE

Architectural and engineering firms will be hired this week to complete an expedited design process on projects that need drawings and specifications generated to get quotes from contractors and building permits through the Lane County planning department. Many new Lane project employees will be hired by Facilities, Management and Planning over the next six weeks in support of the Go Oregon deferred maintenance projects. In addition, many contractors' employees will be employed on the Go Oregon deferred maintenance projects to begin work at Lane Community College in April. All Go Oregon deferred maintenance project employee postings will be re-posted this week to allow a second opportunity for eligible Lane employees to apply as internal candidates. The hiring and planning process will take the majority of FMP's office staff resources for the next six weeks. A storage staging area will be set up just north of building 7 in parking lot N. Lynn Atkins is coordinating the installation of 10 steel containers, a fence, lighting, and a security camera system. FMP staff, Human Resources staff, and Purchasing staff will be extremely busy supporting this effort to meet the Go Oregon stimulus package timelines. All new project employees must be hired and all contractor contracts fully executed by the end of April. We thank you for your understanding and consideration during the next six weeks as we focus on the Go Oregon deferred maintenance stimulus campaign. Contact: Dave Willis, willisd@lanecc.edu

March 3, 2009
DEFERRED MAINTENANCE UPDATE: HIRING UNDERWAY, WEB PAGE UP

Preparation work is well underway for deferred maintenance projects to be funded by $8 million in state stimulus funds. Many postings for jobs related to this work are available online at https://jobs.lanecc.edu. As of February 26, more than 350 people had applied for these postings. Hiring committees are working hard to prepare and interview candidates. Up to 25 positions should be filled by the middle of April.

A temporary project shop/supplies staging area will be set up in parking lot N, close to building 7.

Contractors and suppliers are encouraged to visit the new deferred maintenance web page at www.lanecc.edu/facilities/dm to fill out a template and e-mail it to deferredmaintenance@lanecc.edu by the end of the day on March 13 to be considered for deferred maintenance project work. Invitations to architects and design firms are being distributed and posted on the same web page.

A Deferred Maintenance Leadership Team, including Facilities, Management and Planning staff, instructional deans, and executive level administrators, is meeting weekly to plan and organize this effort. Many thanks to everyone working on this very important project. For more information, contact Dave Willis at willisd@lanecc.edu or (541) 463-5566.


>> Return to Lane's Homepage     >> Return to Facilities Management and Planning Main Page     >> Return to top of page

Lane Community College - Facilities Management and Planning - Building 7, Room 204
4000 East 30th Avenue, Eugene, OR 97405 - (541) 463-5216
Please direct comments about this site to haywardj@lanecc.edu
Revised 10/29/09 (sm)
© 1996-present Lane Community College