Link: Lane Home
 Lane Home Page  |  Search Lane
Contact Us  |  Web Site Accessibility
Community Center for Family Counseling

>> Planning and Construction
  
>> Indoor Environmental Quality
 
Construction Projects
>> Deferred Maintenance
>> Bond
>> Health and Wellness
>> Longhouse
   
>> Trades and Services
   
 
>> Facilities Office
   
>> Transportation
   
>> Safety
   
>> Space Assignment Requests
  
>> Work Requests
  
>> Resources
    
>> Related Sites
   

 

Construction Updates by Building
(links marked with * are .pdf and require Adobe Reader)

Building 1 | Building 2 | Building 3 | Building 4 | Building 5 | Building 6 | Building 7 | Building 8 | Building 9 |Building 10 | Building 11 | Building 12 | Building 13 | Building 15 | Building 16 | Building 17 | Building 18 | Building 19 | Building 24-27 | Center | Airport | Downtown Center | Florence Center | Parking Lots

Building 13

January 12, 2010
PROJECT 448 KEYLESS ACCESS
The contractor, Allied Fire & Security, is currently installing door hardware on Building 7. After work is completed on 7, the next buildings are 6, 16, 19 and Center. Hardware installations on buildings 8, 9, 12, 15, 4, and 13 have been completed to date, though some procedural and hardware/electronic issues remain on these buildings. The remainder of the buildings will be commissioned through winter and spring terms. FMP electricians will be concentrating on the keyless access system over the next several months. Contact Dave Smith, 3433.

September 1, 2009
PROJECT 451 UTILITY SUBMETERING

Meter installations completed this week: water in buildings 41, 49, and Center; natural gas in buildings 44, 49 and Center; electric in buildings 10, 12, 13, 15, 16, 17, 41 and Center. Main isolation valve replacements this week: domestic cold water in buildings 12, 15, 16, 17, and Center. Contact Angela Fazio, 463-3428.

August 10, 2009
UTILITY SHUT DOWN SCHEDULED FOR AUGUST 21, 22, AND 23, 2009
Electricity will be shut down in Building 13 on August 23. Contact Mark Richardson, 463-3426.


>> Return to Lane's Homepage     >> Return to Facilities Management and Planning Main Page     >> Return to top of page

Lane Community College - Facilities Management and Planning - Building 7, Room 204
4000 East 30th Avenue, Eugene, OR 97405 - (541) 463-5216
Please direct comments about this site to haywardj@lanecc.edu
Revised 1/14/10 (sm)
© 1996-present Lane Community College