Construction Updates by Building
(links marked with * are .pdf and require Adobe Reader)
Building 1 | Building 2 | Building 3 | Building 4 | Building 5 | Building 6 | Building 7 | Building 8 | Building 9 |Building 10 | Building 11 | Building 12 | Building 13 | Building 15 | Building 16 | Building 17 | Building 18 | Building 19 | Building 24-27 | Center | Airport | Downtown Center | Florence Center | Parking Lots
Airport
February 16, 2010
BOND UPDATE: AMTF IMPROVEMENTS
The Aviation Maintenance training facility paint booth airflow modifications completed this week. An independent testing company to measure air profile. Rohner will be on site this week to complete exterior finishes. Final electrical and plumbing inspections passed and final building inspection is expected next week. Contact Angela Fazio, 3428.
January 12, 2010
PROJECT 447 CARPET REPLACEMENT AND FLOOR COVERING INSTALLATION
Building 19 hard flooring installation in the storage hallway, room 107 has been completed. Flight Technology, building 44, restroom flooring and carpet replacement is also complete. Contact Angela Fazio, 3428.
PROJECT 458 AMTF IMPROVEMENTS
Aviation Maintenance Technician program paint booth was erected and dried in. Wall insulation and exterior skin will be installed this week. Rohner will be onsite next week to begin start-up and commissioning of the new unit. Contact Angela Fazio, 3428.
September 1, 2009
RTS PARKING LOT EXPANSION
Bids are out for expanding the parking lot at the return-to-service building at the airport. Expect work to begin the week of September 14, and continue for approximately three weeks. Contact Brian McMurray, 5829.
PROJECT 447 CARPET REPLACEMENT/FLOOR COVERING
Carpet replacement for building 19 upper level hallways and classrooms will be completed by September 2. Rubinstein’s Carpet removal on the first floor of building 19 is going to start on Monday August 31 and is expected to be completed by September 4. Building 19 room 104 is scheduled to have the carpet removed on September 3 and replaced on Friday, September 4. Flooring has been ordered for Flight Technology and is scheduled for installation October 30. Contact Mark Richardson, 463-3426.
PROJECT 451 UTILITY SUBMETERING
Meter installations completed this week: water in buildings 41, 49, and Center; natural gas in buildings 44, 49 and Center; electric in buildings 10, 12, 13, 15, 16, 17, 41 and Center. Main isolation valve replacements this week: domestic cold water in buildings 12, 15, 16, 17, and Center. Contact Angela Fazio, 463-3428.
PROJECT 458 AMTF IMPROVEMENTS
Bldg 12 paint booth has been assembled and mechanical/electrical connections are being made. Expect completion week of September 28. The paint booth for RTS building will be ordered this week. Contact Brian McMurray, 463-5829.
August 10, 2009
PROJECT 458 RTS AND BUILDING 12 PAINT BOOTHS
Concrete demolition for new paint booth installation in building 12 will start Tuesday, August 4. Booth installation is scheduled to begin August 17 and should take one week. Contact Brian McMurray, 463-5829.
July 21, 2009
PROJECT 458 RTS AND BUILDING 12 PAINT BOOTHS
Orders have been placed for new paint booths for building 12 and the RTS building at the airport. Demolition of old booth in building 12 is underway. Contact Brian McMurray, 463-5829.
July 14, 2009
PROJECT 458 AMTF AND BUILDING 12 PAINT BOOTHS
New paint booths have been ordered for the return to service building at the airport and for Building 12. Demolition of the old booth in Building 12 is scheduled to begin July 13. Contact Brian McMurray, 463-5829.
June 23, 2009
PROJECT 458 RTS AND BUILDING 12 PAINT BOOTHS
New paint booths for building 12 and the RTS building at the airport will be ordered this week. Contact Brian McMurray, 463-5829.
June 16, 2009
PROJECT 458 AMTF AND BUILDING 12 PAINT BOOTHS
Proposals for new paint booths have been received and are being evaluated. Expect fabrication of booths to begin last week of June. Contact Brian McMurray, 463-5829.
|